Skip to main content

Photo: USCG Press via Wikimedia Commons · Photo source · CC BY 2.0

White House says Trump announced Alaska LNG approval but names no permit or order

by Melinda Communities.News
2 min readPrudhoe Bay to Nikiski, Alaska

President Donald Trump told Southeast Asian leaders this week that "we also just approved" a liquefied natural gas pipeline in Alaska. A White House fact sheet repeated the claim Friday without naming a permit, order or agency.

The Alaska LNG project would carry North Slope gas 807 miles from Prudhoe Bay to Nikiski, with offshoots planned for the Fairbanks, Mat-Su and Kenai areas, according to the Alaska Department of Natural Resources. Its owners have not committed to build it, and the state has not decided whether to grant full rights to cross its land.

"Thanks to a historic investment from South Korea, we also just approved a colossal liquefied natural gas pipeline in Alaska," Trump said Tuesday, according to a clip the White House posted. Friday's fact sheet says South Korea and Taiwan "helped fund" the pipeline.

The project already had its major federal permits. The Federal Energy Regulatory Commission authorized it in May 2020, and the federal permitting dashboard lists its environmental review and permitting as complete as of Dec. 10, 2025.

In October, the White House said Trump had secured a $54 billion deal with Korea and Taiwan to build the pipeline, which it said would cut Alaskans' energy costs by $10 billion. South Korea's trade ministry said the countries had agreed to begin reviewing the project and would decide whether to proceed if it met commercial-reasonableness requirements and Korean legal conditions, according to its Korean-language release, translated by AI. Taiwan said its terms are still to be negotiated.

Adam Prestidge, president of Glenfarne Alaska LNG, told the Resource Development Council on Nov. 11 that Korea was still reviewing the project's financial viability. "That's obviously a big question," he said. He said Glenfarne, which owns 75% of the project, was in "detailed discussions" with the federal Commerce Department on a structure letting South Korea fund its equity, which would mean "an immediate FID," or final investment decision.

The Department of Natural Resources has proposed converting the project's conditional right-of-way leases, which must be converted before construction can begin, into full leases. Even then, the Alaska Gasline Development Corporation, which owns the other 25%, would need the department's written approval for each phase before work starts on state land. The first gravel and camp work, once planned for April 2026, is now planned for 2027.

The department is holding lease hearings online Monday evening and in person Tuesday in Anchorage, with written comments due by 5 pm Wednesday.

Without Korean investment, Prestidge said, Glenfarne would try to finance the project privately. That would take a state tax bill and utility gas deals approved by the Regulatory Commission of Alaska, and a final investment decision would take longer, he said.

Made by our human newsroom with AI. How humans and AI work here · Grow with our newsroom ·

Source: The White House, President Trump Brings Home Billions in Economic Growth and Strengthens America’s Security.