Video Clips
Quoted moments from Alaska public meetings, hearings, and press conferences.

Matt Kissinger
“There may be multiple rounds building up to an fid but you won't achieve a final investment decision until you have sufficient funding to construct the project along with your contingency and additional contingency for contract cost overrun. Risk, et cetera, at that point in time, once that final investment decision, and that's a single vote that happens at a single moment in time. That's what starts the clock on our 180 days.”Alaska Legislature: Senate Finance - June 4, 2026 10:00am · Jun 4, 2026

Frank Richards
“when the legislature created agdc, they also gave an exemption to any project that AGDC was working on that there would be no property taxes during construction. So what you hear from the developer is they're willing to pay a property tax, an alternative volumetric tax during construction.”Alaska Legislature: Senate Finance - June 4, 2026 10:00am · Jun 4, 2026

Matt Kissinger
“Developers have a habit of setting very aggressive FID dates and they do this because it's really the only way to drive everyone who's actually working on a project to a common target. But the knock on effect is it sets this unrealistic FID date out in the public and slowly credibility erodes.”Alaska Legislature: Senate Finance - June 4, 2026 10:00am · Jun 4, 2026

Bert Stedman
“there is some other concerns that some of us have at the table when it's referenced to the state. You know, a lot of it's really easy to assume it come into the legislature, but there has been some interest in accessing other entities of the state if it's the Alaska Railroad, if it's ada, if it's a permanent fund. So there is concern on the structure and how that would be executed.”Alaska Legislature: Senate Finance - June 4, 2026 10:00am · Jun 4, 2026

Matt Kissinger
“that 2mil rate has since morphed into this alternative volumetric tax which we feel also brings a lot more alignment.”Alaska Legislature: Senate Finance - June 4, 2026 10:00am · Jun 4, 2026

Adam Prestidge
“Two of those board members are appointed by Glenn Farn. The first, the chair of the board is Brendan Duvall, the CEO and founder of Glenfarn Group. And the second board member appointed by Glenn Farn is myself, Adam Prestage. AGDC has the right to appoint one board member and they've appointed Frank Richards the president of of agdc.”Alaska Legislature: Senate Finance, 6/3/26, 1:30pm · Jun 3, 2026

Adam Prestidge
“The distinction here is that recognizing the importance of AGDC's role representing the State of Alaska, there are additional components and rights and, and principles that benefit the AGDC minority share and require certain things from Glenfarn”Alaska Legislature: Senate Finance, 6/3/26, 1:30pm · Jun 3, 2026

Matt Kissinger
“Additional capital asks of AGDC or of the state have to have AGDC approvals. That's a really important one. There are no more capital asks of AGDC into 8 star without AGDC's consent.”Alaska Legislature: Senate Finance, 6/3/26, 1:30pm · Jun 3, 2026

Matt Kissinger
“Same with asset distributions. They're not allowed to distribute the assets of eight Star without our approval. So that protects eight Star and the assets within it. That especially the permits and the right of way and things that we've contributed to it.”Alaska Legislature: Senate Finance, 6/3/26, 1:30pm · Jun 3, 2026

Matt Kissinger
“These are the overarching principles that we put in place to truly protect the key issues of importance to Alaskans. So the first one is establish and maintain a substantial operational presence in Alaska. And again, if we see contracts coming through that don't achieve that aim, then AGDC has the right to disapprove of those contracts.”Alaska Legislature: Senate Finance, 6/3/26, 1:30pm · Jun 3, 2026

Matt Kissinger
“The first one is non Alaska aligned contracts. So we have the Alaska Advantage principles that we'll talk about next and we get to review every key contract that is progressed through eight Star and ensure that they're all in line with those principles.”Alaska Legislature: Senate Finance, 6/3/26, 1:30pm · Jun 3, 2026

Adam Prestidge
“In addition we have an independent non voting board member that sits on the board. That person at all times needs to be an Alaska resident. That position is appointed by the mutual agreement between Glenfarn and agdc. That role, that board seat is currently held by Janet Wiese who was formerly the president of BP Alaska.”Alaska Legislature: Senate Finance, 6/3/26, 1:30pm · Jun 3, 2026

Speaker A
“the most recent information I've heard is that it's imminent. I understand it's pushed from what was previously forecasted, but I believe it's still expected the first half of this year.”Senate Finance, 6/2/26, 9am · Jun 2, 2026

Speaker A
“We were recently involved with reviewing the Vogel nuclear power plant down in Georgia. Units 3 and 4 that were completed a few years ago. That project, I believe, ended up at roughly $36 billion and took, I believe it was seven years longer than planned to complete.”Senate Finance, 6/2/26, 9am · Jun 2, 2026

Speaker A
“a Black Swan event is just something that is unplanned for as low probability, but high impact when it does occur. COVID 19 was a great example of a Black Swan event.”Senate Finance, 6/2/26, 9am · Jun 2, 2026

Speaker A
“the pre FID status including gas sales precedent agreements, downstream letters of intent, pipe supply, preliminary agreements and engagement with EPCM and EPC contractors”Senate Finance, 6/2/26, 9am · Jun 2, 2026

Bert Stedman
“As I recall that from those classes that we had years ago on a mega project, if, if you were only 20% or less overrun, that was a successful project.”Senate Finance, 6/2/26, 9am · Jun 2, 2026

Speaker A
“Bent Flyberg is recognized as one of, if not the preeminent researcher of megaprojects. Through his research of Thousands of projects. He's found 92% of megaprojects are over budget, over schedule or both, which he has dubbed the Iron Law megaprojects.”Senate Finance, 6/2/26, 9am · Jun 2, 2026

Matt Kissinger
“we have as AGDC, even prior to Glenfarm coming into the project, we've put out there this assumption of $1.50 and I think we are still confidently within that assumption range.”HFIN-260527-1330 · May 27, 2026

Matt Kissinger
“If you look at Canada versus Alaska, they have It's a fairly well-known resource, but it's an undeveloped resource that requires drilling and development through the life of those projects. It's the Montney and the Horn Rivers, tight, tight oil and gas up in northern BC and Alberta. They have the pipeline that had to go over the coastal range. We get to avoid the coastal range.”HFIN-260527-1330 · May 27, 2026

Frank Richards
“the cost estimate level for the gas treatment plant and the liquefaction are currently a Class 4. And so, as I started off, you know, we were at $44 billion, we reduced it to $38 billion in 2020. And what AGDC did is we had engaged with Fluor as essentially our owner's engineer over the years, and we asked Fluor to keep up with the cost and we would recast that cost estimate”HFIN-260527-1330 · May 27, 2026

Matt Kissinger
“And you see that aside from capital cost, the property tax is the largest single impact on this project.”HFIN-260527-1330 · May 27, 2026

Matt Kissinger
“We had them come in and compare it with every other jurisdiction, especially around the U.S., Canada, but also some overseas jurisdictions. And what they found was that our property tax in Alaska, the way it's structured, assured would result in property taxes a whole order of magnitude, so kind of 10 times higher than the next highest.”HFIN-260527-1330 · May 27, 2026

Andy Josephson
“when we talked to our consultant, Mr. Fulford, yesterday, he didn't suggest that, that, uh, the contract covered price. That was an imperative feature on his slide deck, I think taken from DOR, showing these heat charts where we had to be in the top left corner to reach or come under that $10.41 cost at delivery.”HFIN-260527-1330 · May 27, 2026

Matt Kissinger
“I would suspect— I would expect that any contract going in front of the RCA for utility sales in Alaska would look very different with or without the changes to property tax. Simply because it's more than— it's well over $2 impact per MMBTU, which is the unit of measure that is normally sold in. And so I don't believe that they could just simply absorb it.”HFIN-260527-1330 · May 27, 2026

Matt Kissinger
“In 2016, they brought in Wood Mackenzie, and they asked Wood Mackenzie to do a competitiveness analysis of the project. And Wood Mackenzie said that the project ranked poorly in terms of competitiveness. And they recommended that we adopt a debt-funded third-party tolling structure rather than what would normally be your IOC, your International Oil Company balance sheet financed project.”HFIN-260527-1330 · May 27, 2026

Lyman Hoffman
“we need to get the projected cost of the Trans-Alaska Pipeline and the actual cost, which has been, was substantially higher than doubled. From my recollection.”SFIN-260527-0900 · May 27, 2026

Bert Stedman
“if they need a concession, on a $45 billion project, what are they going to ask for when it's $70 billion?”SFIN-260527-0900 · May 27, 2026

Bert Stedman
“we need to look at that. Mr. Chairman, and then get into more discussion on the dilution issue, the equity dilution issue, which the state would be facing as a residual owner right now at 25% with no equity participation coming into the project yet from, from a third party.”SFIN-260527-0900 · May 27, 2026

Bert Stedman
“this committee has spent year after year after year dealing with construction projects all across the state and we have massive inflation and cost escalations over the last decade to the point where we've had to put in tens of millions of dollars backfill for OMB— excuse me, not OMB, but our contractors to facilitate the completion of their contracts”SFIN-260527-0900 · May 27, 2026

Nicholas Fulford
“it is clear that one or more companies with a very significant balance sheet would have to enter the project with equity in order for it to get across the finish line.”SFIN-260527-0900 · May 27, 2026

Nicholas Fulford
“once FID has taken on those 3 subunits, the state's 25% of the holding company may or may not have significant value.”SFIN-260527-0900 · May 27, 2026

Bert Stedman
“that integrated structure you talked about, I think for the state's 25% share, included our royalties plus a gas tax to create that 25% alignment with the 3 major producers in that project, which seems to be quite dissimilar from the merchant structure or this tolling structure that you just mentioned.”SFIN-260527-0900 · May 27, 2026

Bert Stedman
“In this case, Clunth Farm doesn't. They couldn't finance this thing if they had to by themselves. So I think we're— the scale difference between the previous three participants under 138, including the state with its financial assets and its taxing authority, far eclipses the structure of Glenfarm.”SFIN-260527-0900 · May 27, 2026

Nicholas Fulford
“with the current arrangement, it's not surprising, frankly, that there is some degree of concern over confidentiality, capital costs, and so forth.”SFIN-260527-0900 · May 27, 2026

Nicholas Fulford
“unlike the Gulf Coast projects, which involve smaller capital investment but higher operating costs, for example, gas purchase and shipping, Alaska's quite the opposite. And although it's a gas project, it's almost easier to look at it as if it were a toll road or an airport or some kind of infrastructure project because most of the value for AKLNG is going to be in that midstream”SFIN-260527-0900 · May 27, 2026