Speaker A
22:58 - 23:27
"We were recently involved with reviewing the Vogel nuclear power plant down in Georgia. Units 3 and 4 that were completed a few years ago. That project, I believe, ended up at roughly $36 billion and took, I believe it was seven years longer than planned to complete."
“We were recently involved with reviewing the Vogel nuclear power plant down in Georgia. Units 3 and 4 that were completed a few years ago. That project, I believe, ended up at roughly $36 billion and took, I believe it was seven years longer than planned to complete.”
- Speaker
- Speaker A
- Timestamp
- 22:58 – 23:27
- Community
- Alaska News
- Location
- Juneau, AK, USA
- Captured at
- June 2, 2026
From the transcript
To the chair. We were recently involved with reviewing the Vogel nuclear power plant down in Georgia. Units 3 and 4 that were completed a few years ago. That project, I believe, ended up at roughly $36 billion and took, I believe it was seven years longer than planned to complete. It was the first new nuclear project in the United States in many decades.
Related Coverage
Consultant warns Senate Finance that Alaska LNG faces megaproject risks
Independent megaproject consultant warns Alaska Senate Finance that 92% of megaprojects exceed budget or schedule, with LNG projects averaging 70% cost overruns, directly challenging optimistic timelines for the state's proposed gas pipeline and export terminal.