Speaker A
22:58 - 23:27
"We were recently involved with reviewing the Vogel nuclear power plant down in Georgia. Units 3 and 4 that were completed a few years ago. That project, I believe, ended up at roughly $36 billion and took, I believe it was seven years longer than planned to complete."
“We were recently involved with reviewing the Vogel nuclear power plant down in Georgia. Units 3 and 4 that were completed a few years ago. That project, I believe, ended up at roughly $36 billion and took, I believe it was seven years longer than planned to complete.”
To the chair. We were recently involved with reviewing the Vogel nuclear power plant down in Georgia. Units 3 and 4 that were completed a few years ago. That project, I believe, ended up at roughly $36 billion and took, I believe it was seven years longer than planned to complete. It was the first new nuclear project in the United States in many decades.
Independent megaproject consultant warns Alaska Senate Finance that 92% of megaprojects exceed budget or schedule, with LNG projects averaging 70% cost overruns, directly challenging optimistic timelines for the state's proposed gas pipeline and export terminal.