Alaska LNG isn't hiring yet, and spring is the soonest it might start

by Cale Green · draft by Bill AlaskaNews
2 min readAlaska

The company developing the Alaska LNG gas pipeline isn't hiring construction workers yet and probably won't before spring, its workforce lead told students and career counselors in an online session this week.

Hiring would come with what the company calls its final investment decision, when the project's owners commit the money to build it. Glenfarne hasn't made that decision, and its president has said the company can't pinpoint when it will.

Asked for "some candy" on when people might be working, Ella Ede, Glenfarne Alaska LNG's community affairs and workforce development lead, pointed to spring.

"I really think realistically, the soonest we would see, you know, the ... what we call final investment decision and starting to employ people for these jobs would probably be the spring," she said, according to a transcript. "I would love to say winter." With "a new administration and everything else going on in the political world," she said, spring or summer is more realistic.

The project's dates have slipped before. In February, the company told federal regulators that its first construction work would start April 15, 2026. That work has since moved to 2027.

The project "did have some delays based on things that happened in Juneau," Ede said. She described two paths forward: a tax bill through the Legislature, where one stalled this year, or working through the U.S. Department of Commerce. On the private path, Glenfarne Alaska LNG President Adam Prestidge said Nov. 11, milestones outside the company's control make it "impossible for us to pinpoint exactly when FID will occur."

If the project goes ahead, Glenfarne estimates about 800 workers for a first year of road, gravel and camp work; a peak of 12,000 when the two phases of construction overlap; and about 1,000 full-time jobs over 30-plus years.

The state's numbers are smaller. A state labor department analysis released in August projected about 6,600 Alaska LNG workers at peak construction. Its report assumed an investment decision in 2026, which hasn't happened, and found that demand would exceed what Alaska's workforce and training programs can supply.

Ede said the project would need equipment operators, welders, truck drivers and unskilled laborers, including "students right out of high school," whom it would train.

Glenfarne has no target for hiring Alaskans, she said. It signed an agreement last summer with 18 Alaska labor unions to provide most of the labor and put Alaska workers first. But "even if we were to ... hire every Alaskan we can, we're still going to have to bring in people from out of state," she said.

Made by our human newsroom with AI. Reviewed by Cale Green. How humans and AI work here · Grow with our newsroom · Transcript byLucas Brown

This article is based on a public meeting of Alaska Department of Labor and Workforce Development — Alaska Labor & Workforce: Mining Industry ().