Alaska gives BlueCrest until Jan. 31 to start drilling for Cook Inlet gas

by Cale Green · draft by Walter AlaskaNews(3h ago)
3 min readAnchor Point, Alaska

Alaska on Tuesday gave BlueCrest Alaska Operating until Jan. 31 to start drilling for a large, undeveloped supply of natural gas under Cook Inlet, and until March 31 to get it flowing.

If the company misses either deadline or any other condition, the state says it will put BlueCrest back in default. In August, Natural Resources Commissioner John Crowther warned that without development, the company's Cosmopolitan Unit near Anchor Point should be given up or handed to an operator that can develop the gas. "The time for delay has ended," he wrote.

Cook Inlet gas production has roughly halved since 2010, and ENSTAR, which serves about 157,000 customers, told legislators in August it was 18 days short of gas for a normal winter. It had expected up to 1.5 billion cubic feet from BlueCrest starting Sept. 1; its president said that gas wasn't coming.

Matanuska Electric Association told lawmakers in June that residential bills would jump $21 to $31 a month once it begins importing pricier liquefied natural gas, after its Cook Inlet contract expires in 2029, and ENSTAR said its customers would see similar increases starting in 2033.

Crowther lifted BlueCrest's default Monday, finding that the company had lined up financing, restarted work on its drill rig and filed a plan with a firm date to start drilling. The next day, he and Haley Paine, director of the Division of Oil and Gas, approved that plan with conditions. Neither decision says how much gas the first well is expected to produce or when it could reach a buyer.

The financing rests on two agreements BlueCrest signed Sept. 10 with NBS Holding LLC. The state reviewed them confidentially and found "definitive evidence" of committed financing to refurbish the rig, modify facilities and begin drilling for the first phase of the gas project.

Rig work began early this year and stopped in May when BlueCrest's funding ran out. On Nov. 4, state staff saw the rig being refurbished at the company's Anchorage shops. BlueCrest's own plan aims to start drilling Dec. 15.

BlueCrest must now tell the state right away about any technical problem that would make it miss either date, then file a new schedule within five business days, with assurance it has the money to finish drilling. It must also send updates every other Friday. Crowther wrote that if the company falls short in the future, the record would support enforcement "on an expedited basis."

BlueCrest has pumped oil and small amounts of gas from the unit for 10 years. Its wells start on an onshore pad on the southern Kenai Peninsula and reach out under Cook Inlet; there are no offshore facilities. The gas the state wants developed sits in a rock layer called the Tyonek, above the deeper reservoirs BlueCrest produces from now.

The state put the unit in default in May 2025, mainly because BlueCrest hadn't lined up the financing for the Tyonek gas that its 2024 and 2025 plans promised. BlueCrest argued in December 2024 that there wasn't enough gas storage or demand, and that developing the gas before 2030 would be "premature and financially imprudent." The state disagreed, saying utilities' uncontracted gas needs would grow sharply in 2028.

BlueCrest also changed which well it will drill first, to one called H-15, after more engineering review. Crowther wrote that the change "is expected to accelerate delivery of gas to Alaska consumers."

A separate review of the boundary of BlueCrest's oil-producing area is still pending.

Made by our human newsroom with AI. Reviewed by Cale Green. How humans and AI work here · Grow with our newsroom ·

Source: State lifts BlueCrest's Cosmopolitan default and gives it until Jan. 31 to spud a Tyonek gas well and March 31 for first gas.