Crews clear route for Bradley Lake power line ahead of Dixon Diversion expansion
Crews cleared trees along the route of a new power line between the Bradley Lake powerhouse and its dam, Homer Electric Association reported Wednesday. The line will support the Dixon Diversion, a planned expansion of the hydroelectric plant northeast of Homer.
Bradley Lake supplies about 10 percent of the electricity on the Railbelt, the grid that runs from Homer to Fairbanks, according to an Alaska Energy Authority presentation. The expansion would raise its yearly output about 40 percent. The authority estimates it would displace about 1.5 billion cubic feet of natural gas a year by 2031.
The authority's timeline calls for bidding in 2027, construction starting in 2028 and completion in 2031. Exact timing depends on federal reviews, including a license change the authority expects next summer, and on final funding approval.
The authority owns the 120-megawatt plant, open since 1991, and Homer Electric operates it. The Dixon Diversion would carry meltwater from the Dixon Glacier 4.6 miles through a tunnel into Bradley Lake. The dam and spillway would be raised so the lake can sit about 16 feet higher.
The existing single-phase line between the powerhouse and the dam is old and needs replacement, authority staff told the utilities in September. The clearing was timed around federal bird-protection limits so the new line can be built in 2027, according to minutes of the utilities' Bradley Lake management committee. The authority expects to approve installation of the new line, estimated at about $17 million, in February, once funding is in hand.
An earlier addition, the West Fork Upper Battle Creek Diversion, completed in 2020, carries glacial water into the lake and delivers about 10 percent more energy, the authority says. Homer Electric said that diversion was winterized and isolated on Oct. 24.
The authority's current budget puts the expansion at about $436 million, not including interest. The Railbelt utilities that buy the plant's power would repay the authority's debt through their power sales agreement, authority staff told the board in July.
In a resolution signed in October, the management committee gave preliminary approval to an interim financing program of up to about $151 million for work through fiscal 2028, though it said that was not yet approval for the authority to take on the debt. The program cannot begin until each utility's board approves it. Those votes are due within 45 days of an updated cost estimate the authority expected to complete by mid-November.
What did you make of this story? (no account needed)
Made by our human newsroom with AI. How humans and AI work here · Grow with our newsroom ·
Keep Alaska News free for everyone.
No paywall, ever. Members pay so everyone can read the meetings and records Alaska News covers.
Get Alaska News in your inbox
Create your free account and get the day’s top stories around 6 each morning, in a few minutes’ read.
Top stories, around 6 each morning.
Stories on what you follow, on Sundays.
Source: Homer Electric Association, Homer Electric Association: November 2026 | MONTHLY CEO REPORT.














Comments
Sign in to leave a comment.
No comments yet. Be the first to share your thoughts.