Curtis Thayer is the Executive Director of the Alaska Energy Authority, the state's energy office responsible for reducing the cost of energy across Alaska.
Affiliations
Homer Electric spent about four hours cut off from the grid during battery maintenance
“The line that currently serves from Anchorage down to Homer is 50 years old.”

Crews clear route for Bradley Lake power line ahead of Dixon Diversion expansion
“it's a directional drill 5 miles through a mountain, 16-foot in diameter, and puts more water into Bradley, and we raise the dam 16 feet to accommodate that additional water”

State energy board moves to accept up to $150 million for a second Railbelt power line
Alaska's energy board moved to take up to $150 million in Defense Production Act money for a second Southcentral-Interior line. The other $268 million? TBD.

Alaska takes a new look at the 705-foot Susitna dam as Cook Inlet gas runs short
“So even if we decide that we want to pursue this, perfect case, we're a good 15 years away. This does not solve our problem today.”

State energy board votes on nearly $5 million solar loan for Red Dog Mine
The state energy board votes Thursday on a nearly $5 million loan for solar at Red Dog Mine, sized to stay just under the line where the Legislature gets a say.

Comment closes on giving the energy authority state land at Bradley Lake at no cost
“the best time to build hydro was 30 years ago. Bradley proves that at 4.5-cent power. The next best time to build hydro is today.”

State energy board to vote on nearly $5 million loan for solar at Red Dog Mine
Red Dog Mine makes all its power from diesel and cuts power to parts of the mine in summer. A state board votes Nov. 5 on a nearly $5 million loan toward solar.

Alaska Energy Authority board votes Nov. 5 on a new look at the shelved Susitna dam
Alaska's energy authority votes Nov. 5 on a new look at the shelved Susitna dam, saying "time is of the essence" to catch tax credits worth up to half its cost.

A second power link to Kenai would run under Cook Inlet
“would give us redundancy on the Cook Inlet that we do not have”

Three Homer Electric generators failed at once, and hydro covered the gap
“So if you have 120-megawatt plant, you're not getting the full capacity necessarily when you need it.”

Comments on the $400 million Bradley Lake expansion close Friday
“the best time to build hydro was 30 years ago”

Enstar tells legislators it's 18 days short of gas for winter
Enstar told legislators it's 18 days, about 3 Bcf, short of gas for a normal winter after two supplies fell through, with deals underway still leaving a gap.

A $400 million expansion of Bradley Lake hydro would power about 30,000 homes and cut Southcentral's gas use
A $400 million Bradley Lake hydro expansion would power about 30,000 homes and offset 1.5 billion cubic feet of gas a year, easing Southcentral's gas crunch.

A $413 million cable would give Kenai and Anchorage a second power link
One transmission path links Kenai to Anchorage. A $413 million subsea cable would add a second, if AEA can raise the half that isn't federal.

Railbelt ratepayers will repay up to $100M for a Bradley Lake expansion built around federal tax credits
“The tax credits could be up to $200 million.”

Bradley Lake expansion has carried three price tags in four months as the comment window closes
“In order to potentially qualify for tax credits, the dam must be 16 feet to create the head pressure to provide additional power to hopefully qualify for the alternative measurement standards. The tax credits could be up to $200 million.”

Alaska Energy Authority lifts ban on consecutive chair terms
Alaska Energy Authority board voted January 31 to allow its chair and vice chair to serve consecutive terms, removing a two-year rotation rule to maintain leadership continuity during a $206.5 million Cook Inlet submarine cable project.