Frame from "Nome Port Commission Work Session and Regular Meeting- Sept. 17, 2026" · Source
Spur demolition begins at Port of Nome as city lines up $1 million match
Demolition of the spur at the Port of Nome has begun, Port Director and Project Manager Joy Baker told the Nome Port Commission on Thursday, and the city has locked in $1 million toward its share of the federal construction cost. The spur comes out to clear the way for a causeway extension in 2027.
"Kiewit has started removing armor stone off the top of Desperre, and we've had a couple of meetings out there on site with them talking about traffic control, access for the trucks," Baker said. Trucks are turning off Causeway Road onto a purpose-built ramp to stockpile removed rock on the beach. Port staff now meet with the contractor daily or every other day on haul plans.
The Nome City Council approved an amended Norton Sound Economic Development Corporation lease at second reading Monday, covering the lot between the freezer plant and harbor office. On signature, NSEDC transfers $1 million for a 19-year lease paid in advance, counting toward the city's cost share. Baker listed a $1 million Denali Commission contribution and $300,000 from an adjacent property owner, with roughly $1 million still unresolved.
Alaska Marine Lines' final freight barge of the season arrives between Sept. 23 and 26, which Baker said would be the hardest test yet of sharing the dock with construction.
This article is based on a public meeting of City Of Nome — Nome Port Commission Work Session and Regular Meeting- Sept. 17, 2026 ().
AI-assisted. No editor review is on record for this article. Who is accountable. Transcript byWalter AlaskaNews
Stay informed. Support what matters.
Free, permanent access to local news you can verify. Subscribe to support Bill AlaskaNews and go ad-free.
Related Coverage
Nome port's national security designation could save city $132 million in construction costs
Alaska News · 1mo ago
Nome is becoming America's first deepwater port in the Arctic
Alaska News · 2mo ago
King Cove road materials arrive on scene as local workers hit another milestone in the development of a contested project
Alaska News · 1mo ago
Eight welders certify in Nome as a $400 million port job looms
Alaska News · 1mo ago
Repairs begin on the Nome-Council Highway, four years after Merbok
Alaska News · 3d ago
Comments
Sign in to leave a comment.
No comments yet. Be the first to share your thoughts.