Homer Electric spent about four hours cut off from the grid during battery maintenance

by Walter AlaskaNews
2 min readHomer, Alaska

Homer Electric Association's system on the Kenai Peninsula was cut off from the rest of the Railbelt grid for about four hours on Oct. 30 after a tree reportedly contacted a transmission line, the cooperative says.

The fault came while Homer Electric's battery storage system was undergoing scheduled maintenance. Dispatchers started the Soldotna Combustion Turbine plant to keep the system stable, according to the cooperative's November 2026 Monthly CEO Report, released Wednesday.

Operating while disconnected from the larger grid is called islanding. While islanded, the cooperative carries more spinning reserve on its own, generation kept running and ready to pick up load. The battery had been in maintenance since Oct. 26, and the report said that limited its available capacity when the fault hit. Crews finished repairs on 10 Megapacks, the system's battery units, and it returned to full service after the maintenance ended.

Islanding can affect what members pay. Staying connected to the larger grid reduces the spinning reserve Homer Electric carries on its own and spares it from running the Nikiski Combined Cycle plant at minimum load, the cooperative's July report said. It pointed in part to fewer hours of islanding when it cut its power cost charge, which mainly reflects the cost of fuel and of power bought from the Bradley Lake hydroelectric project, by 5.5% that quarter.

Homer Electric expects about 117 days of scheduled islanding over the next 12 months, its October report said.

The November report places the Oct. 30 fault between the University and Indian substations on the Railbelt transmission system. The Alaska Energy Authority calls the connection between the Kenai Peninsula and Anchorage a "single point of failure."

"The line that currently serves from Anchorage down to Homer is 50 years old," Curtis Thayer, the authority's executive director, told a joint legislative hearing Aug. 20. "Some segments are 60 years old."

The authority's proposed Cook Inlet PowerLink, a 38-mile undersea cable estimated at $413 million, would add a second connection. A federal grant covers $206.5 million, and the authority lists about $142 million more as still required. Its board made that money its top request to the Legislature on Nov. 5.

Companies' technical and budget pricing for supplying and installing the cable is due Dec. 15. The authority's target for finishing the project is 2032.