AI image
A Chugach substation rebuild draws a neighbor's concern over transformers near a home
Chugach Electric's plan to rebuild its Campbell Lake substation in south Anchorage goes before the Planning and Zoning Commission on Monday, with a member of the project's community advisory group asking for changes to protect a next-door resident from two transformers she says would sit close to his home.
Kate Petoskey, who serves on the Working Group Chugach convened for the rebuild, submitted a comment asking that if the utility won't move the transformers — which she said a neighbor reports would sit less than 4 feet from his house — it at least plant "a treed buffer" next to the property "to lessen the negative impacts and loss of quiet enjoyment." She noted the neighbor is a first responder who could be dispatched to an incident at a Chugach substation.
Petoskey said the Working Group met three times, in February, March and April, and that concerns about the neighboring lot came up both there and at Chugach's May community meeting, but that the group was not reconvened to discuss where the transformers would go. The Working Group issued no formal position on the project, she said, and a recent serious injury will keep her from Monday's hearing.
Chugach says the rebuild will replace aging equipment, improve reliability and meet current safety standards, with concrete barriers around the transformers to muffle noise. The utility is seeking two variances — to reduce landscaping widths on several property lines and to raise the fence height by six inches — which it says are needed to keep mature vegetation and secure the site. The Planning Department's staff report found the project meets the criteria with minimal impacts and recommended approval.
The substation, built in 1976, serves about 4,600 properties in south Anchorage. The rebuild follows a 2024 order from the Municipal Board of Adjustment requiring new public outreach; a proposed 65-foot communication tower has since been dropped. Construction is expected to begin in 2028. The comment record includes no response from Chugach to Petoskey's request.
Source: Planning and Zoning Commission, Planning and Zoning Commission: Planning and Zoning Commission Case 2026-0098: Campbell Lake Substation CUP ().
Drafted with AI. Edited by Cale Green (1 revision). No full editor review is on record. Who is accountable.
Stay informed. Support what matters.
Free, permanent access to local news you can verify. Subscribe to support Walter AlaskaNews and go ad-free.
Related Coverage
Anchorage planning commission approves Chugach substation rebuild over neighbor's objection
Alaska News · 1mo ago
Neighbors got the tower dropped from a south Anchorage substation rebuild
Alaska News · 4mo ago
Anchorage clears a substation plat on quake-prone Port ground
Alaska News · 2w ago
Port of Alaska seeks road realignment for Chugach Electric substation
Alaska News · 3w ago
Chugach seeks industrial zoning for its campus, dropping a buffer
Alaska News · 1mo ago

Comments
Sign in to leave a comment.
No comments yet. Be the first to share your thoughts.