Luke Boland
25:55 - 26:25
"Wasilla Fishhook Main Street rehab. This PDA has been advancing, this one's certified, the funding request is over at Federal Highways for approval. They had some questions on the conditional right-of-way cert for this project, which we got resolved yesterday."
“Wasilla Fishhook Main Street rehab. This PDA has been advancing, this one's certified, the funding request is over at Federal Highways for approval. They had some questions on the conditional right-of-way cert for this project, which we got resolved yesterday.”
And then last one on the list for July, Wasilla Fishhook Main Street rehab. This PDA has been advancing, this one's certified, the funding request is over at Federal Highways for approval. They had some questions on the conditional right-of-way cert for this project, which we got resolved yesterday. So hopefully we're seeing approval from FedHighways here pretty soon, and we'll be working on getting this one out to bid here this month. Might be tight for July, but looking, looking good.