More than 100 land deals stand between Alaska and a safer KGB Road
Before the state can start fixing one of Mat-Su's known safety problems, it has to buy land from more than 100 separate property owners.
That's the holdup on Knik-Goose Bay Road, where safety corridor improvements are a stated top priority for the transportation department and still aren't expected to go out for bid until March 2027 — meaning construction wouldn't begin until that summer at the earliest. "We've got over 100 property acquisitions needed to deliver this," said Luke Boland, the department's preconstruction engineer in Anchorage, who added that the work touches just about every utility in the corridor.
It's one of a string of Alaska road and airport projects sliding into 2027 and beyond, each stuck behind a different kind of obstacle. A seaplane ramp at Ketchikan Airport is waiting on an Army Corps of Engineers permit. A generator replacement at the Gustavus ferry terminal is waiting on nothing but a signature — a federal funding authorization that hasn't been signed. If it lands this month, the project advertises; if not, August.
In a state where the building season runs a few months, a modest delay costs a full year. A Northern Region project on the Tope Cut-Off slipped six to ten months after environmental review turned up more complexity than expected — enough to knock it out of the 2027 construction season entirely and into 2028.
This article is based on a public meeting of Alaska Department of Transportation and Public Facilities — Alaska DOT&PF: Tentative Advertise Schedule Monthly Update: July 2026 ().
Made by our human newsroom with AI. How humans and AI work here · Grow with our newsroom Transcript byLucas Brown
Watch key moments from the source meeting. Click to expand.
Stay informed. Support what matters.
Free, permanent access to local news you can verify. Subscribe to support Walter AlaskaNews and go ad-free.
Related Coverage
Anchorage faces federal funding freeze if transportation plan misses December deadline
Alaska News · 3mo ago
Alaska DOT letter shows $563 million in contracts, projects record year, warns of match shortfall
Alaska News · 2w ago
Ketchikan's long rebuild of the road toward Saxman inches ahead, with a waterside path and a tangle over land
Alaska News · 2mo ago
Ketchikan viaduct repairs slip to 2030, the second delay since August
Alaska News · 1d ago
Trucks keep hitting the Tudor Road overpass. The rebuild is years out
Alaska News · 2mo ago

Comments
Sign in to leave a comment.
No comments yet. Be the first to share your thoughts.