“Ketchikan-Saxman to Surf Street pavement rehabilitation, South Tongass. Big project here, major right-of-way effort ongoing right now. Definitely some risks for that December date there. There's some local issues as well, but I'm holding that as best as we can.”
- Speaker
- Kirk Miller
- Timestamp
- 7:16 – 7:45
- Community
- Alaska News
- Location
- Alaska
- Captured at
- July 20, 2026
From the transcript
Next up, another ER project, Haynes Roadway and Culverts, holding December on that one, no changes from last month. And last for calendar year 2026 is Ketchikan-Saxman to Surf Street pavement rehabilitation, South Tongass. Big project here, major right-of-way effort ongoing right now. Definitely some risks for that December date there. There's some local issues as well, but I'm holding that as best as we can.
Related Coverage
More than 100 land deals stand between Alaska and a safer KGB Road
Alaska can't fix KGB Road until it buys land from 100-plus owners. Elsewhere a Gustavus generator waits on a signature. Everything's sliding to 2027.