Kirk Miller
2:41 - 3:03
"Gustavus Ferry Terminal generator replacement. We are waiting for a a design— a funding authorization from FHWA. For some reason, this has not been signed yet, but we're all ready to advertise. If we can get that authorization back from FHWA, that will hit July. If not, we're probably going to scoot that one into August."
“Gustavus Ferry Terminal generator replacement. We are waiting for a a design— a funding authorization from FHWA. For some reason, this has not been signed yet, but we're all ready to advertise. If we can get that authorization back from FHWA, that will hit July. If not, we're probably going to scoot that one into August.”
Gustavus Ferry Terminal generator replacement. We are waiting for a a design— a funding authorization from FHWA. For some reason, this has not been signed yet, but we're all ready to advertise. If we can get that authorization back from FHWA, that will hit July. If not, we're probably going to scoot that one into August.