State seeks comment on Cordova runway rehabilitation that could briefly halt jet service
The Alaska Department of Transportation and Public Facilities is taking public comment through Dec. 18 on a plan to rehabilitate the main runway at Cordova's airport. Work is expected to begin in spring 2028, depending on funding.
The project could at times close the runway to Alaska Airlines jets. At the project's first open house in March 2024, project manager Chris Johnston said the runway would be too short for jet landings while crews replace a culvert beneath it. Closures could last about 48 hours, according to the department's meeting summary.
Crews normally repave a runway half at a time so planes can keep using the other half, but the culvert work rules that out here. Johnston said closures would be coordinated with Alaska Airlines, cargo carriers and the Coast Guard, and that the department typically gives 45 days' notice. A comment recorded at that meeting noted that August and September, the peak of silver salmon fishing and lodge season, are the busiest months, and that June and July would be the most logical time for closures.
The department says the runway pavement at Merle K. (Mudhole) Smith Airport is degraded and beyond its useful life, with uneven surfaces, ponding water and inconsistent lighting. Under the plan outlined in a Nov. 3 letter seeking comments, crews would rehabilitate about 4,300 feet of the runway, reconstruct about 3,200 feet, shift the runway about 45 feet east and add about 400 feet of new runway at the east end. Culverts, edge lights and signs would also be replaced.
The plan would remove the Engineered Material Arresting System at the runway's west end. The system was installed in 2007 and 2008 to help slow landing aircraft, since the runway could not be extended far enough to provide the standard 1,000-foot safety areas at both ends.
At the Cordova City Council meeting Wednesday, residents were urged to submit comments, with a warning that the work could be very disruptive because a culvert must be fixed and large Alaska Airlines jets cannot use half a runway. Vice Mayor Kasey Kinsman said he was glad the runway work had moved ahead of a planned perimeter fence, though "there will be some disruptions to service, more than likely."
The fence is a separate project the department expects no sooner than 2029, depending on funding. The department's letter says the Federal Aviation Administration would review the runway project through an environmental assessment because of anticipated wetland impacts, pending a final FAA decision. In 2024, the department had expected a categorical exclusion, to be finished by spring 2027.
The second open house is Tuesday, Dec. 1, from 5 to 7 pm in Community Room A at the Cordova Center. Comments can be made there or by email to [email protected] through Dec. 18, according to the public notice.
What did you make of this story? (no account needed)
Made by our human newsroom with AI. How humans and AI work here · Grow with our newsroom ·
Keep Alaska News free for everyone.
No paywall, ever. Members pay so everyone can read the meetings and records Alaska News covers.
Get Alaska News in your inbox
Create your free account and get the day’s top stories around 6 each morning, in a few minutes’ read.
Top stories, around 6 each morning.
Stories on what you follow, on Sundays.
Assembled from public records the newsroom collected.














Comments
Sign in to leave a comment.
No comments yet. Be the first to share your thoughts.