AI image
State-backed Alyeschem plant reaches construction milestone
A state-backed chemical plant planned for Prudhoe Bay has completed installation of its foundation piles, the project's first announced construction milestone since breaking ground in May.
The Alaska Industrial Development and Export Authority said the final pile was installed Sept. 12. Its latest update does not provide a revised project cost or completion date. When Alaska News covered the groundbreaking, AIDEA said the facility was expected to begin operating in late 2027.
The state's support is not a $70 million grant. AIDEA has authorized and executed project loan financing of up to $70 million. Public board minutes describe private investors matching AIDEA's contributions dollar for dollar. The financing calls for repayment of principal and interest, plus a permanent royalty tied to plant output.
Alyeschem is designed to produce methanol and ultra-low sulfur diesel from North Slope natural gas and captured carbon dioxide. Methanol is used in oil-field operations to prevent freezing and corrosion. Producing it at Prudhoe Bay could reduce reliance on supplies shipped to Alaska and trucked north on the Dalton Highway.
AIDEA estimates the project will support about 80 construction jobs and 15 permanent operating positions. Those figures, along with projected emissions and transportation savings, come from the project's backers.
The foundation work confirms that construction is underway. AIDEA's public project page does not state how much of the authorized loan has been drawn or provide a current independent assessment of the late-2027 startup target.
Source: Alaska Industrial Development and Export Authority, Alaska Industrial Development and Export Authority: Alyeschem Construction Continues to Advance with Completion of Foundation Pile Installation.
Made by our human newsroom with AI. Reviewed by Cale Green. How humans and AI work here · Grow with our newsroom
Stay informed. Support what matters.
Free, permanent access to local news you can verify. Subscribe to support Melinda Communities.News and go ad-free.
Related Coverage
Alyeschem breaks ground on North Slope methanol plant
Alaska News · 4mo ago
Alaska LNG developer says financing secured, eyes 2027 start
Alaska News · 4mo ago
Alaska's first big AI data center clears a hurdle on the North Slope
Alaska News · 2mo ago
Alaska LNG lease filing lists state gasline corporation as 25 percent owner
Alaska News · 3d ago
Alaska LNG report targets 2028 completion for in-state pipeline
Alaska News · 5d ago

Comments
Sign in to leave a comment.
No comments yet. Be the first to share your thoughts.