Skagway Borough Manager Emily Deach is asking the Borough Assembly to add $250,000 for a temporary community laundry and $490,000 more for the West Creek Levee. Her memo, dated Monday, proposes four changes to the borough budget for fiscal year 2027. The Assembly takes up the changes at a public hearing Thursday, Nov. 19, at 7 pm, according to the meeting agenda.

The laundry building at the Garden City RV Park is set to be torn down as part of a water and sewer project, which voters backed with up to $6.5 million in bonds.

Deach proposes a prefabricated 40-foot laundry container as a temporary community facility, paid for with sales tax. It is tentatively sited behind the old Police Department building south of 1st and State. The unit would hold two 70-pound washers, two commercial dryers, residential stacked washer and dryer units, a laundry sink and ceiling heaters.

The base estimate is $219,400. An official quote that includes card readers for the machines and shipping is still pending, and water and sewer fees, site work, concrete, electrical and communications would add to the cost.

The levee request corrects a budget error Deach flagged last week, when she asked the Assembly to award the project's only bid while acknowledging her draft budget carried just $1.21 million for it. The memo puts the total project cost at $2,172,000, with $500,000 funded in fiscal year 2026.

"It is clear that I erroneously entered the figure for the FY27 budget, leaving the project short," Deach wrote.

The fix would raise the fiscal year 2027 amount to $1.7 million: $300,000 in land funds and $1.4 million in sales tax. The borough received a single bid, $2.078 million from Hamilton Construction LLC, below the engineer's estimate, according to the Nov. 13 award memo. The Assembly will also consider awarding that contract Thursday. Construction is scheduled for fall and winter 2026-27.

The Welcome Garden budget would drop from $352,000 to $293,000 in fiscal year 2027, all from port funds. A cost estimate based on design drawings dated Oct. 16 raises the total by about $100,500, to roughly $452,500. Construction is planned for fall 2027. Planting moves to spring 2028 because, Deach wrote, it "should not be done in the Fall and must be done after the infrastructure is in place."

The last change adds $50,000 from the water and sewer fund to study alternatives for the borough's leaking wooden water tanks. The current year's budget already holds $50,000 to fix them, but a week of Public Works repairs did not stop the leaks. Deach wrote that the tanks are critical for holding the town's water supply.

An updated budget summary attached to the memo shows the cruise passenger fund ending fiscal year 2027 with an estimated reserve of about $1.32 million, after a $2 million transfer to the clinic that Deach proposed earlier this month.

Made by our human newsroom with AI. How humans and AI work here · Grow with our newsroom ·

Source: Municipality of Skagway, Skagway manager proposes $250,000 temporary laundry container to replace the Garden City RV Park laundry, and corrects the levee budget, ahead of Nov. 19 budget hearing.