Skagway weighs a $2.08 million fix for a West Creek flood levee near Dyea
Skagway's Borough Assembly votes Thursday on whether to spend up to $2.08 million shoring up a flood levee on West Creek near Dyea, about $868,000 more than the borough's draft 2027 budget sets aside for it.
Borough Manager Emily Deach says the shortfall is her mistake. "The draft FY27 budget includes only $1,210,000 for the project – this was my error," she wrote in a memo to the Assembly on Friday. She plans to ask the Assembly separately to amend the budget.
The levee is a rock-covered embankment that runs about 2,000 feet along West Creek's south bank, ending at the West Creek bridge, where the creek flows into the Taiya River near Dyea, the gold rush townsite at the start of the Chilkoot Trail.
A 2022 inspection found the levee in good, stable condition overall, but with a 20- to 30-foot gap in its rock armor. The gap posed no current risk, engineers wrote, but it left the end of one section exposed to floodwater getting around it, which "could quickly undermine and destroy large segments of the levee wall under extreme flood conditions." Closing it would also guard against flooding onto the road, they wrote.
The borough commissioned that inspection while it explored building a housing subdivision on land south of the levee.
Hamilton Construction, a Skagway company, was the only bidder; its price came in just under the engineer's estimate of about $2.17 million. Most of the money would go to rock. About $1.3 million of Hamilton's bid is for riprap, the heavy rock armor laid along a bank to keep moving water from wearing it away.
The work would cover two stretches of the bank, one about 720 feet long and the other about 30 feet, and must be done by April 1, 2027.
The price has grown. When the Assembly set aside $500,000 in sales tax for the project this year, the budget listed its total cost at $1 million.
Deach's memo says her budget amendment will account for that $500,000 and the work expected to be done this year, but it doesn't say how big the change will be. The amendment isn't in Thursday's meeting packet yet.
The Assembly meets at 7 pm Thursday at City Hall. The same agenda includes a public hearing on the draft 2027 budget, which is set for a final vote Dec. 3.
PND Engineers, which did the 2022 inspection, wrote that the levee appeared to have been in place for many years or decades and was overgrown with alders. It recommended clearing the brush and closing the gap, among other fixes.
In June 2023, Deach, then the deputy manager, told the Assembly "the state of the levee needs to be addressed before lots are developed or sold" in the proposed S'áxt' Héeni (Devil's Club River) Subdivision.
In March 2024, the Assembly voted 6-0 to pay RESPEC $160,000 to survey and design the levee work and study hydrology for the proposed subdivision. Then-Assembly member Orion Hanson, now the mayor, said the levee was not completed after the 2002 flood and the road is eroding, the minutes record.
What did you make of this story? (no account needed)
Made by our human newsroom with AI. Reviewed by Cale Green. How humans and AI work here · Grow with our newsroom ·
Get Alaska News in your inbox
Create your free account and get the day’s top stories around 6 each morning, in a few minutes’ read.
Top stories, around 6 each morning.
Stories on what you follow, on Sundays.
Source: Municipality of Skagway, Skagway's only bid for West Creek levee work is $2.08 million, and the manager says her draft budget carries $1.21 million for it by mistake.












Comments
Sign in to leave a comment.
No comments yet. Be the first to share your thoughts.