Nikiski's old LNG export terminal clears a federal safety review to import gas

by Cale Green · draft by Walter AlaskaNews
3 min readNikiski, Alaska

Federal safety regulators said Tuesday that a plan to import gas through Nikiski's idle LNG terminal meets federal siting rules.

The Kenai LNG Terminal opened in 1969 to ship Cook Inlet natural gas out of Alaska. Now its owner wants to bring gas in, as Southcentral Alaska faces a forecast shortage of its own.

The terminal could send out up to 20 billion cubic feet of gas a year. That's about a third of the 60 billion cubic feet ENSTAR Natural Gas says Railbelt utilities typically need in a year.

In June, Matanuska Electric and ENSTAR told lawmakers that imported gas could be priced at as much as double current rates. Chugach Electric's chief executive, Arthur Miller, told members in May that the utility will import if it has to.

Tuesday's finding isn't a permit. The Federal Energy Regulatory Commission still has to decide whether to approve the project, and its review is behind its own schedule.

The terminal has sat idle but maintained since 2015. FERC approved a smaller import plan there in 2020, to bring in up to four tanker loads a year for the neighboring refinery.

Harvest Alaska bought the terminal's owner, Trans-Foreland, from Marathon in October 2025. In January, the company asked FERC to expand that plan so the gas could also reach the region's utilities.

The gas would go to the Marathon refinery next door and, through existing pipelines, to Chugach Electric, ENSTAR, Matanuska Electric and Homer Electric, according to the application.

ENSTAR, which joined the FERC case as a potential customer, called 20 billion cubic feet "not insignificant." But it said the project "alone will not eliminate the need" for more gas. ENSTAR said its contract with the state's largest gas producer, which represented 85% of its supply, ends in 2033. In 2024, it said, it entered an exclusivity agreement with Glenfarne to develop a different import terminal.

Fairbanks' Golden Valley Electric Association also joined the case, calling itself "agnostic to solutions."

Harvest bought the terminal last year and said they were aiming for first imports in the first half of 2028. In a Nov. 19 filing, it said repairs to the 1969 dock, partly to fit modern LNG tankers, are preliminarily expected between April and October 2027.

Tankers would unload liquefied gas at that dock, and new equipment would turn it back into gas. The work would stay inside the terminal's existing fenced site.

The safety agency set three conditions. In one leak scenario it studied, flammable vapor could reach past the terminal's southern property line. That land belongs to the neighboring Agrium fertilizer plant, which closed in 2007. Before installing pumps on that side, the company needs a final legal agreement with the neighbor.

It must also show that its systems can detect and stop a high-pressure leak within 30 seconds, and file a final hazard analysis. The nearest residential property is about 0.8 miles away.

FERC invited 21 tribes and Native corporations to consult, including the Kenaitze Indian Tribe and the Salamatof Native Association. No replies appear in the record. The group Our Children's Trust filed comments opposing fossil fuel approvals on constitutional grounds.

FERC planned to release its environmental assessment Oct. 16, followed by a 30-day comment period. That date passed with no assessment and no new schedule in the record.

Made by our human newsroom with AI. Reviewed by Cale Green. How humans and AI work here · Grow with our newsroom ·

Source: Federal safety regulators clear siting of Nikiski LNG import expansion that could bring 20 Bcf of gas a year to Southcentral.