Haines seeks an engineer to plan disinfecting the sewage it pipes into Portage Cove

by Walter AlaskaNews
3 min readHaines, Alaska

Haines Borough is hiring an engineering firm to plan how its sewage plant will start disinfecting wastewater piped into Portage Cove. The borough posted the job Nov. 19, and firms have until Thursday, Dec. 17, to apply.

The plant currently does not disinfect, the borough says, and a federal permit gives Haines until 2030 to meet final limits on bacteria in its sewage. The borough warned in 2023 that without grants, meeting the permit's requirements could mean "doubling, tripling or even quadrupling" monthly sewer fees.

A Haines home pays a flat $61.80 a month for sewer service this year, under the borough's rate schedule, up from $54.75 in 2022. The schedule already sets the charge to rise to $63.65 next July.

Public Facilities Director Edward Coffland issued the 2023 warning in comments on the draft permit. He estimated a disinfection system would cost $3.9 million to build and $1,091,350 over five years to staff and supply with chemicals. The U.S. Environmental Protection Agency responded that "compliance and cost are not factors when evaluating the need for WQBELs," its term for limits set to protect water quality, and left the limits unchanged.

The plant gives sewage primary treatment only, which removes solids. It runs under a Clean Water Act waiver, known as a 301(h) waiver, that allows that lower level of treatment, and serves about 1,800 residents, according to an EPA fact sheet.

The permit measures fecal coliform and enterococcus, bacteria that signal human or animal waste. An interim limit lets the plant's fecal coliform average 977,000 per 100 milliliters over a month. The final limit is 200. From 2016 to 2021, Haines' discharge averaged about 597,000.

The permit took effect Nov. 1, 2025, and sets yearly deadlines. The first, a facility plan choosing a disinfection method, was due one year after the permit took effect, a deadline that passed this month. Records do not show whether Haines met it or sought an extension. Final design is due at two years, and funding and a construction contractor at three.

The borough's scope of work says it "handles compliance dates with EPA and ADEC," the state Department of Environmental Conservation, separately from this contract.

The engineer must compare disinfection options including ultraviolet light, chlorine removed before discharge, and a cold-water process such as peracetic acid. "No action cannot be the preferred alternative," the scope says, and the borough intends to keep its waiver. The plan must also account for seasonal loads from cruise ships and RVs.

The state awarded the borough a $550,000 Alaska Clean Water Fund loan, fully forgiven, to design plant upgrades that include disinfection. The plan's funding chapter is to address that loan, a request to the Alaska State Legislature, and borough capital funds or sewer rates. Records do not show what the planning contract itself will cost.

EPA's compliance database lists four other reports the permit required by January and April as "unachieved and not reported." EPA's record shows no formal enforcement and no penalties.

Until the plant meets the final limit, the permit requires signs near the outfall warning against bathing or harvesting shellfish to eat raw there.

Made by our human newsroom with AI. How humans and AI work here · Grow with our newsroom ·

Source: Haines Borough, Haines seeks an engineer for its sewage disinfection plan, a step its EPA permit set for one year after Nov. 1, 2025.