Alaska DEC seeks a construction manager for a new Hooper Bay sewage lagoon

by Walter AlaskaNews(1h ago)
2 min readHooper Bay, Alaska

The Alaska Department of Environmental Conservation opened a request for proposals Wednesday seeking a firm to manage construction of a new sewage lagoon and sewer line in Hooper Bay. Proposals are due Dec. 11 at 2 pm Alaska Standard Time.

The request for proposals says the village's current lagoon operates beyond its design capacity and no longer meets modern regulatory standards. It also says Typhoon Merbok flooding breached the lagoon in 2022.

The single-cell, 5-acre lagoon was built in 1994 to serve the local school. It now takes flows from a school built in 2006 and more than 200 households connected since 2007. Settlement and seepage through the berms have also weakened the structure, according to the request, though crews finished temporary berm repairs this spring.

The replacement will be a lined, two-cell lagoon in a natural depression about a mile north of the community. A 2018 engineering report by CRW Engineering had favored building a new lagoon on higher ground just north of the old one, but later soil testing ruled that site out. The request says suitable sites for a lagoon this large are hard to find in Hooper Bay. Design engineers with Summit Consulting Services found the new site, and a March soil study confirmed it.

Design has reached 95 percent and passed a third-party review. The design team expected to finish it by mid-November and then submit it to the department's Wastewater Program, which is expected to issue approval to build in early 2027.

Soil conditions require building the berms over at least two winters, the document says. Crews will rough them in during the winter of 2027-2028, then let the embankments rest, thaw and drain the following summer. Crews will finish the berms and install the liner in the winter of 2028-2029, or later if needed.

Local workers will do the building under a force account arrangement, with the labor provided by the community. The winning firm will manage, schedule and supervise that crew but may not do physical construction itself. It must provide an on-site superintendent, or recommend one for the community to hire, with at least five years of experience managing construction projects in rural Alaska communities. The contract is expected to run from Feb. 1, 2027, through June 30, 2030.

The request estimates the management contract at $1 million or more. That figure is separate from the project's total funding: the department's state fiscal year 2026 project list shows about $34.2 million in funding to date for the Hooper Bay lagoon's design and construction. Minority- and women-owned firms receive a five-point preference.