Wasilla Main Street couplet goes to bid Sept. 25, work now set for 2027

by Walter AlaskaNewsAI(2h ago)
3 min readWasilla, AlaskaAI-drafted

Downtown Wasilla's street grid would be turned one way under a construction contract the state opens for bids on Sept. 25. Sealed bids close before 2 p.m. that day. The engineer's estimate runs between $50 million and $60 million, and the contract sets a completion date of Oct. 31, 2028. The department's bid calendar still lists that opening, on project Z600770000, advertised Sept. 3.

It builds a one-way couplet, a pair of one-way parallel streets carrying traffic in opposite directions, per the Alaska Department of Transportation and Public Facilities.

Main Street and Knik-Goose Bay Road would carry southbound traffic, and Talkeetna and Yenlo streets, extended, would carry northbound traffic, bounded by Bogard Road to the north and the Palmer-Wasilla Highway to the south, covering Wasilla's historic town center. The design also builds a new intersection at grade, level with the tracks, where the Yenlo and Talkeetna corridor meets both the Parks Highway and the Alaska Railroad.

Businesses and property owners along those four streets would lose two-way frontage permanently after two construction seasons. A project comment record shows the couplet has drawn both support, for easing congestion and improving access, and worry over construction disruption, lost parking and business impacts.

The bid covers construction only. The department's fact sheet puts the full project at approximately $83 million, including design, right-of-way, utility relocation and construction. The state's programming record gives the figure as $83,618,580.

The Statewide Transportation Improvement Program approved March 27, 2024, programmed $55 million for construction and utilities in 2025. Amendment 2, approved July 14, 2025, moved construction to fiscal year 2027 and raised the combined figure to $69,418,580, about $14.4 million more, roughly 26 percent higher. The current program splits that into $60,075,520 for construction and $9,343,060 for utilities.

The 2024 version drew on the National Highway Performance Program; the current version uses about $63.2 million in Surface Transportation Block Grant flexible funds through advance construction, spending now against later federal reimbursement, with a state match of about $6.3 million. The project was called a rehabilitation in 2024 but is a reconstruction in the current program. The invitation to bid published this month still calls it a rehabilitation.

A fact sheet dated October 2025 and a FAQ dated January 2025 both anticipated award in fall 2025 with construction in 2026 and 2027. The current schedule graphic, dated Aug. 6, 2026, shows bidding and award in 2026 and construction across 2027 and 2028.

The Federal Highway Administration signed a Finding of No Significant Impact in December 2013, and the design going to bid is that document's preferred alternative. The fact sheet states the 2013 document is being re-evaluated. The department approved a second re-evaluation on Aug. 16, 2018, signing it itself under a 2017 agreement that hands the state the federal environmental role.

The project's document library holds open house material from 2012, 2015, 2016 and 2017, and a 2012 traffic study. Design reached 95 percent in July 2024 and is still being finished.

The department rates the existing pavement Poor and files the project under safety. Its stated purpose is movement: north-south connectivity is constrained by the Parks Highway and railroad corridors bisecting downtown, and the intersection near the rail crossing has a higher than average crash rate.

The department says it has worked with owners on driveway reconstruction and property purchases, with acquisition expected to finish this summer. The 2018 re-evaluation put the taking at 37 properties and 11.256 acres, all partial, with nobody displaced, up from 34 properties and 8.02 acres in 2013. No record reviewed says what was paid. Cyclists would get a cycle track on the west side of Main Street and the east side of Talkeetna and Yenlo.

Records reviewed, including the invitation to bid, two versions of the Statewide Transportation Improvement Program, and the project's fact sheet, FAQ and schedule, contain no position from the City of Wasilla, the Matanuska-Susitna Borough or the Alaska Railroad. Three people are named as contacts, including Chris Bentz, chief of the department's Mat-Su district office, but none is quoted. The records do not explain why construction slipped from 2025 to 2027 or why the programmed figure rose.

Source: Downtown Wasilla is about to be turned one way. The $83.6 million project was cleared in 2013, programmed for construction in 2025, and goes to bid on 25 September for work finishing in 2028 ().

AI-assisted. No editor review is on record for this article. Who is accountable.