Mat-Su weighs selling more gravel for Nova's refinery before Nova has a lease

by Cale Green · draft by Walter AlaskaNewsFrom
2 min readPort MacKenzie, Alaska

The Mat-Su Borough Assembly is set to decide Tuesday whether to sell more borough gravel to build the pad for Nova Minerals' antimony refinery at Port MacKenzie, though the company doesn't yet have a lease for the land.

Nova's contractor, Geo Civil Solutions, asked for about 30,000 cubic yards from the borough's Lorraine pit, near the refinery site. The borough manager approved the first 14,000 in mid-November as "a way for Nova to begin pad development" while the Assembly considered the rest, according to a borough memo. Tuesday's resolution would add the other 16,000.

Neither the memo nor the resolution says what the contractor is paying. The borough's fee schedule bases commercial gravel sales on market value. The memo cites a 2013 ordinance that approved selling gravel from the Lorraine pit for less than market value to tenants on borough land.

The memo says Nova is using the gravel "to develop their site on borough-owned land," but it doesn't call Nova a tenant. In July, Port Director Dave Griffin told the borough's Port Commission that Nova held a land use permit and that its lease was in draft, according to draft minutes.

On Sept. 1, the commission recommended that the Assembly lease 42.78 acres of port land to Nova's Alaska subsidiary for 20 years. Griffin told commissioners Nova was investing $20 million and that improvements would stay with the borough.

He and the borough's land manager, Joe Metzger, said the lease would reach the Assembly in mid-November. It isn't on the Assembly's Nov. 17 or Dec. 1 agenda.

The gravel sale is on Tuesday's consent agenda, a list of items the Assembly takes up in a single vote, without discussion, unless a member asks to pull one. The borough administration recommends approval.

The refinery is meant to turn antimony, a metal used in ammunition that the U.S. hasn't mined since the early 1990s, into concentrate for the Department of War, which granted Nova $43.4 million. Nearly 500 tons of secondhand processing equipment came ashore at the port in September, before the plant had its state air permit. In October, Nova told federal securities regulators the state had approved its mine and refinery plans.

The Assembly meets at 6 pm Tuesday in Palmer.

Made by our human newsroom with AI. Reviewed by Cale Green. How humans and AI work here · Grow with our newsroom ·

Source: Matanuska-Susitna Borough, Mat-Su Assembly asked to add 16,000 cubic yards of borough gravel to a sale for Nova's Port MacKenzie refinery site.