Mat-Su Assembly picks costlier northern route for Engstrom-Trunk road
Assembly picks costlier northern route for Engstrom-Trunk road, over landowners' objections
The Matanuska-Susitna Borough Assembly chose the costlier of two routes for a new road between Engstrom and Trunk roads Tuesday, over the objections of landowners who testified they will not sell right-of-way.
Members adopted the resolution selecting Northern Route 1, estimated at $21 million to $31 million. The southern alignment is estimated at about $9 million to $10 million. Voters approved $2.5 million for it in November 2021.
Public Works Director Tom Adams told the assembly the northern route delivers the better long-term transportation network. Two community councils, the Planning Commission and two road service area boards had recommended the southern route.
Assembly member Stephanie Nowers said the borough picked a route "without boots on the ground because the landowners have not allowed us on their property."
The main motion first failed, then passed after a successful motion to reconsider. "It passed with Assemblymember Bernier, Bowles, and Nowers opposed," the clerk reported.
No funding source is identified for either alignment. Adams said design milestones and any eminent domain decision return to the assembly.
This article is based on a public meeting of Matanuska-Susitna Borough — Mat-Su Borough: Assembly Meeting - September 15 ().
AI-assisted. No editor review is on record for this article. Who is accountable. Transcript byWalter AlaskaNews
Watch key moments from the source meeting. Click to expand.
Stay informed. Support what matters.
Free, permanent access to local news you can verify. Subscribe to support Walter AlaskaNews and go ad-free.
Related Coverage
Mat-Su commission backs the $9 million road route over the $30 million one
Alaska News · 1mo ago
ENSTAR raised its gas line relocation estimates and Mat-Su road budgets absorb the cost
Alaska News · 4w ago
Mat-Su voters will decide whether the borough can tax valley-wide for big road projects
Alaska News · 1mo ago
A Seward Highway rebuild that doubled to $1.4 billion is back on Anchorage's plan, over objections
Alaska News · 2mo ago
Mat-Su cut school walking paths from its short-term road list
Alaska News · 1w ago

Comments
Sign in to leave a comment.
No comments yet. Be the first to share your thoughts.