Denali repaving bid lets Riley Creek campground loops close in turn next summer

by Maggie AlaskaNews(8m ago)
2 min readRiley Creek Campground, Denali National Park and Preserve, Alaska

The Federal Highway Administration put the repaving of Riley Creek Campground roads in Denali National Park and Preserve out to bid Thursday. The contract terms let each of the campground's three loops close for about four weeks between early May and late July 2027.

Those closures overlap the 2027 visitor season, though the first window opens May 2, before the season's scheduled mid-May start. Riley Creek is the park's largest campground, with room for tents and RVs up to 40 feet. Campground and bus reservations for 2027 open Dec. 1, according to the park's current conditions page.

The National Park Service's list of proposed projects describes the work as repairing the campground road subgrade and repaving the surface with asphalt. It plans a single construction season, with portions of the campground closed for up to a month at a time on a rotating basis.

The solicitation covers 2.02 miles of road and sets the order of closures. Bear Loop and its section of the Connector Trail may close from May 2 to May 28. Caribou Loop, the Caribou Approach and their Connector Trail section may close from May 29 to June 27. Wolf Loop and its Connector Trail section may close from June 28 to July 26.

The Denali Park Road is also affected. At Mile 14.6, the contractor may close the road to public traffic from 11 pm to 5 am and must reopen it to two-way traffic by 5 am each morning. No transit or tour bus may be held more than 30 minutes.

Public access to the U.S. Post Office building at Riley Creek must stay open at all times.

Crews may not work over the Memorial Day, Juneteenth, Independence Day and Labor Day weekends. The contractor must publish notices in local newspapers and on local radio at least five days before work begins.

The park plans to restore public bus service to the west end of the Park Road in 2027. Separate road repairs under a $6.2 million contract began Sept. 18, the morning after the 2026 season's last bus.

Bids are due at 2 pm Dec. 22. The solicitation estimates the work at between $5 million and $10 million and sets a completion date of Sept. 26, 2027. A public comment draft of Alaska's Statewide Transportation Improvement Program lists about $4.4 million for the project in 2026.

The winning bidder owes a baseline schedule within 25 days of award, and no ground-disturbing work can start until it is approved. The actual closure dates depend on that schedule.

Made by our human newsroom with AI. How humans and AI work here · Grow with our newsroom ·

Source: Federal Highway Administration.