Anchorage plans $5.94 million 4th Avenue rebuild contract with YH Constructors

by Walter AlaskaNews(53m ago)
3 min readAnchorage, Alaska

The Municipality of Anchorage's purchasing department told YH Constructors Thursday that it intends to award the company a $5.94 million contract to rebuild 4th Avenue between G and E streets. The Anchorage Assembly must approve the contract before it is signed. That vote is tentatively set for Dec. 1.

YH's low bid runs about $1.56 million, or roughly 36%, over the engineer's estimate of $4.38 million. Six companies bid when the city opened bids Nov. 4, and every bid topped the estimate. The invitation to bid had projected construction costs between $3 million and $5 million.

HPM, Inc. bid $6.12 million, Southcentral Construction $6.22 million, Granite Construction $6.55 million, Roger Hickel Contracting $8.12 million and QAP $8.29 million. The preliminary bid abstract lists all six as local vendors.

Most of the gap lies in roadway and storm drain work, where YH bid $4.18 million against an estimate of $3.09 million. Traffic and lighting work came in at $1.73 million, against $1.25 million estimated.

The city's 2026 approved capital budget listed 2024 bond money for this block and estimated the segment's cost at $8.5 million. It said design, easement acquisition and utilities were paid for with earlier bonds.

Senior Construction Buyer Melanie A. Clark signed the Intent to Award letter. It tells the company not to start work, buy materials or sign subcontracts until both sides sign the contract.

The project removes traffic signals at 4th and G and at 4th and F, replacing them with curb bulbs and raised intersections at both corners. It replaces 12 street lights, 37 pedestrian lights and about 4,484 square yards of sidewalk. Crews will rebuild the storm drain, repave the street and swap existing tree wells for raised precast ones with soil cells. The work falls under a Community Workforce Agreement, which the invitation to bid describes as an agreement between the contractor and the organized labor unions.

Addendum No. 2, issued Oct. 26, sets the schedule. Field work begins when the right of way opens in mid-May 2027. The contractor then has 90 days to reach substantial completion and 30 more days to finish. The city can withhold $1,000 a day if substantial completion runs late and $500 a day if final acceptance does.

Most work must happen at night, from 7 pm to 9 am, between Memorial Day and Labor Day. The contractor may close 4th Avenue between G and E streets, one lane of G Street between 3rd and 5th avenues, and F Street between the alleys. Lane and road closures require at least 72 hours' notice on electronic message signs.

Pedestrians must be able to get through the whole corridor, since sidewalks are the only way into some businesses. A parking garage being built on the south side of 4th between G and F streets is set to open in spring 2027, and its only ramp sits on G Street. The contractor must keep that ramp open.

ENSTAR will lay a new 8-inch plastic gas line in the south parking lane, replacing a 6-inch steel main that conflicts with the new pedestrian lighting. ENSTAR is expected to finish the rest before the contractor starts the second phase, on the south side.