Aleknagik council opposes Nuyakuk River hydro license as proposed

by Walter AlaskaNewsFrom
2 min readAleknagik, Alaska

The Aleknagik City Council passed a resolution Friday opposing a federal license for a hydroelectric plant on the Nuyakuk River "as currently proposed." It asks regulators to require more independent study first.

Aleknagik is one of five communities the plant would power, with Dillingham, New Stuyahok, Ekwok and Levelock. The village councils in two of them, New Stuyahok and Ekwok, have already passed resolutions opposing the project.

Nushagak Cooperative wants to build the 10.8-megawatt plant at Nuyakuk Falls, about 60 miles north of Dillingham and about 4 miles inside Wood-Tikchik State Park, according to its draft license application. It would have no dam spanning the river. An intake above the falls would send no more than 30% of the river's flow, a limit set by state law, through a tunnel to a powerhouse below them.

The communities it would serve run entirely on diesel, brought to Dillingham by boat or air and barged up the Nushagak River, Will Chaney, the cooperative's chief executive, wrote to the Federal Energy Regulatory Commission in August. The draft's projected savings add up to about $5.2 million a year.

The resolution, signed by Mayor Jane Gottschalk, cites "the lack of demonstrated broad support among affected regional communities." It asks the commission to require more study of effects on fisheries, streamflow, subsistence and the park, and more consultation with communities and tribal governments, before it decides.

The city backed studying the project in 2019, but the resolution says that was not unconditional support for construction or licensing.

New Stuyahok Village Council opposed the project 7-0 in March 2025, and in December 2025 asked to be removed from all plans. Ekwok Village Council opposed it in December 2024. Both councils said the project threatens their ancestral land and the subsistence way of life of tribes on the Nushagak.

Commission staff listed 38 items for the cooperative to address, from the racks that would keep fish out of the intake to how construction equipment would reach the site. The National Marine Fisheries Service wants an environmental impact statement and says the design remains largely conceptual. Bristol Bay Native Corporation said it is too soon to take a position.

The draft puts construction at $535.2 million, plus $65 million for engineering, permitting and supervision. Bristol Bay Native Corporation puts the cost at $600 million.

The commission, not the city, decides whether to license the plant. It is taking comments on the draft through Dec. 31, after extending the deadline from Nov. 16 because the window overlapped with subsistence and commercial fishing. The draft says the cooperative will file its final application after Jan. 2, 2027, and the commission says people can comment again after that.