Cover image for article: AIDEA commits $25 million to drill under the West Susitna road

AI image

AIDEA commits $25 million to drill under the West Susitna road

by Bill AlaskaNews(13h ago)
2 min readSusitna River, AlaskaAI

The Alaska Industrial Development and Export Authority committed up to $25 million on Wednesday, Aug. 26, to drill the ground under a road that does not yet have a constructible design, and its own resolution names the three private resource projects the road would serve: Nova Minerals' Estelle antimony and gold project, U.S. GoldMining's Whistler gold prospect, and Terra Energy's coal project in the Susitna basin.

The board drew the money from its revolving fund and took the item up immediately after an executive session on AIDEA projects including West Susitna. The authorization reaches backward as well as forward, covering work already committed or incurred.

The program is scoped to the 2026-2027 field season and covers dozens of proposed bridge, culvert and material sites along the corridor, roughly 448 drilling days with crews and rigs moved by longline helicopter. The Alaska Department of Transportation and Public Facilities portion is estimated at about $18.6 million, with engineering and permitting work running into 2027. The largest single piece is in-water pier drilling at two crossings of the Skwentna River.

The board approved the road as a development finance project in 2019 and accepted state appropriated funds for an earlier predevelopment phase in 2021. The House Finance Committee removed $94 million in federal receipt authority for the project from the capital budget, after hours of divided public testimony.

The resolution also says the road would give the public year-round access to thousands of acres of state land on the west side of the Susitna River for recreation and settlement. At the Alaska Sustainable Energy Conference in May, AIDEA Executive Director Randy Ruaro said of West Susitna: "we're accessing minerals, but we're also providing on that project recreational access and other general access." Trout Unlimited, on its conservation page, calls the same corridor a project that "stands to compromise the future health of our public fish and wildlife resources."

The board authorized a margin of about $1.1 million above identified needs, partly because the in-water drilling at the Skwentna crossings cannot be priced until access is determined.

Permitting is the critical path. Applications to the Army Corps of Engineers, the Department of Natural Resources and the Department of Fish and Game must be submitted before any drill turns, along with historic preservation consultation.

AI-assisted, reviewed by editors. Spot an error?

Reviewed by Cale Green and News Bot