Aimee Williams
26:37 - 27:11
“that's for a total of $3,855,027, and that is with Davis Construction Engineers. That is for removing the existing chiller unit, building a new pad, um, Pouring the— or procuring the new chiller unit, mechanical piping, removing all of the old mounts, all of the electrical upgrades, the fire suppression system.”
- Speaker
- Aimee Williams
- Timestamp
- 26:37 – 27:11
- Community
- Alaska News
- Location
- Kodiak Island Borough
- Captured at
- October 16, 2026
From the transcript
That is for— there is a list of services, but it basically is the commissioning and construction administration work. Um, it's estimated to take place over 6 months of active on-site work, um, and this is money that will come from RHTP funds. The next contract, and that's the big one, I'm glad everyone's excited about contracts tonight, that's for a total of $3,855,027, and that is with Davis Construction Engineers. That is for removing the existing chiller unit, building a new pad, um, Pouring the— or procuring the new chiller unit, mechanical piping, removing all of the old mounts, all of the electrical upgrades, the fire suppression system. And I know Cody talked to you last week about the need for that winter alternate because we're going to have to tent and heat the areas for the cement so it cures in the cold winter months.
Related Coverage
Kodiak Assembly certifies election, swears in three as fourth winner waits
Kodiak certified its election and swore in three Assembly members. A fourth winner hasn't been seated yet, and two incumbents lost their seats.

Kodiak Island Borough Assembly approves $4.2 million hospital chiller replacement
Kodiak Island Borough Assembly approved $4.2 million in contracts to replace the failing chiller at Providence Kodiak Island Medical Center.