0:34
Paul Trissel
27:25 - 28:00
“$40 Million, we'll go with something that's going to cost us about $3.5 million, is what we found.”
- Speaker
- Paul Trissel
- Timestamp
- 27:25 – 28:00
- Community
- Alaska News
- Location
- North Pole
- Captured at
- October 29, 2026
From the transcript
$40 Million, we'll go with something that's going to cost us about $3.5 million, is what we found. And so the, the course of the last year and a half, they've done flow studies, hydrology studies. We just got done with geotechnical work, borings on trying to use where our force main is going behind the high school out to the Tanana, cut into that, run it on just the inside of the dike, run it down the dike to the new location, and, and have a new outfall.
Related Coverage
North Pole needs $3.5 million to move its sewage outfall before daily fines start
After 13 or 14 years of back-and-forth with the state, North Pole must find $3.5 million to move its sewage outfall in about 3.5 years or face daily fines.