Aimee Williams
25:54 - 26:15
“The total project cost is $4,239,116, with $3,801,380 coming from the RHT FPP funds themselves, and $437,736 coming from the hospital R&R fund. In the first contract, that is for a contract with AMC Engineers in the amount of $102,005.”
- Speaker
- Aimee Williams
- Timestamp
- 25:54 – 26:15
- Community
- Alaska News
- Location
- Kodiak Island Borough
- Captured at
- October 16, 2026
From the transcript
All right, take it away. Thank you, Mr. Mayor. Staff is asking the assembly to concur with the proposed project implementation and project delivery approach for the chiller replacement project, uh, with the money that we have received from the Rural Health Care Transformation Project. The total project cost is $4,239,116, with $3,801,380 coming from the RHT FPP funds themselves, and $437,736 coming from the hospital R&R fund. In the first contract, that is for a contract with AMC Engineers in the amount of $102,005.
Related Coverage
Kodiak Assembly certifies election, swears in three as fourth winner waits
Kodiak certified its election and swore in three Assembly members. A fourth winner hasn't been seated yet, and two incumbents lost their seats.

Kodiak Island Borough Assembly approves $4.2 million hospital chiller replacement
Kodiak Island Borough Assembly approved $4.2 million in contracts to replace the failing chiller at Providence Kodiak Island Medical Center.