White House restates $150 million for Beluga-Healy line; source of $268 million share unclear

by Cale Green · draft by Melinda Communities.News(2h ago)
1 min readAlaska

A White House release Thursday, Oct. 8, credited Vice President JD Vance with announcing that the Department of Energy "will invest $150 million" in a 223-mile transmission line between Beluga and Healy. The department's own announcement Monday, which Vance highlighted that day at a Fairbanks rally for Sen. Dan Sullivan, said "up to" $150 million, as Alaska News reported.

The department calls the project's $418 million total, which includes $268 million in planned non-federal funding, a preliminary planning estimate. The White House release gives no construction schedule, and neither federal release identifies who will supply the non-federal share.

The corridor has appeared in state planning before. A 2024 Alaska Energy Authority presentation described a 240-mile overhead high-voltage direct current line from Beluga to Healy, estimated then at $730 million. The authority's 2050 Railbelt plan lists $418 million for new Anchorage-Healy transmission, the same figure as this project's planned total.

The 230-kilovolt overhead line would run from the Beluga substation through West Susitna and Willow to existing infrastructure in Healy, according to a release from Alaska's congressional delegation. The Beluga plant, completed in 1974, has eight turbines and 385 megawatts of capacity, according to the Alaska Energy Authority, the project's sponsor.

Assembled from public records the newsroom collected.