Valdez council weighs a $32 million bond vote, including $7 million for Meals Avenue

by Cale Green · draft by Walter AlaskaNews(21h ago)
3 min readValdez, Alaska

The Valdez City Council votes Tuesday on whether to ask voters to let the city borrow up to $32 million for a new solid waste baler facility, a waterline to its container terminal and rural roads, and to repay the city for its rebuild of Meals Avenue.

If the council agrees, the question goes to voters at a special election Feb. 2.

Here's where the money would go, according to a staff summary and the city manager's report:

  • $9 million for a new solid waste baler facility, replacing the city's baler

  • $7.5 million to replace the waterline serving the Valdez Container Terminal

  • $7 million to reimburse the city for Meals Avenue

  • $6.5 million for rural roads, including the Corbin Creek Subdivision

  • $2 million for interest and the cost of issuing the bonds

Some amounts have changed since October, when a budget presentation listed planned bonds of $12 million for a baler facility and $10 million for the first phase of rural roads.

The Meals Avenue money would pay the city back for a street rebuild it's paying for now. The resolution covers costs "paid or to be paid."

That project is rebuilding Meals Avenue from Pioneer Drive to Robe River Drive, along with East Chena and East Bremer streets and Robe River Drive out to the Valdez High School student parking lot. It includes new pavement, curbs, sidewalks and a bike path, plus storm drain catch basins, five fire hydrants and new streetlights, according to the city's contract summary.

The council approved a $6.3 million contract with Wolverine Supply in March, the lowest of three bids.

Early in the project, the contractor began working seven days a week and more than 11 hours a day "due to being behind schedule," Eric Voorhees, a senior project manager for the city's construction manager, DOWL, wrote in an Oct. 12 letter to the city. Some final items can't be finished this fall, and Wolverine is expected to complete them in 2027, he wrote.

DOWL's own contract grew by $38,965 in October, to $630,903; the city's report attributes the increase to the contractor's extended hours and days. The amendment covers about $16,500 DOWL had already spent beyond the time-and-materials part of its budget, plus one more week of inspection, which DOWL believes "will encompass the final week of paving." DOWL wrote that it will seek more amendments, including for inspection in 2027.

The two contracts now total about $6.96 million. About $7.06 million was available in the project's account when the council awarded the paving contract in March.

That same month, the council approved a resolution keeping open the option to repay costs of two phases of its paving program, including Meals Avenue, with borrowed money. A staff memo noted that state law limits how much property tax Valdez can collect, including on oil and gas property, but there is "no limitation on taxes to pay bonds."

These would be general obligation bonds, backed by the city's full faith and credit. Property taxes could be levied "without limitation as to rate or amount" to repay them, the resolution says, and a majority of voters must approve them under the city charter and the state constitution.

The city manager's report lists the bond under the council's priority of setting money aside each year for deferred maintenance on critical infrastructure. Valdez paid off one bond and prepaid another this year, and its scheduled debt payments for 2027, before any new bonds, are about $1.4 million, according to the October presentation.

The city plans to place the bonds directly with a bank, which the council would pick Dec. 15, before the election, according to a bond timetable. If voters approve, the timetable calls for the bonds to close March 4, with project awards at the council's March 16 meeting.

The council's 7 pm meeting Tuesday also includes a public hearing on the city's 2027 budget and a resolution asking the governor to declare the 2026 Prince William Sound pink salmon fishery an area impacted by economic disaster, according to the meeting agenda.

Editor's note: This story was updated to combine our earlier stories on the DOWL contract amendment and the $32 million bond question, which includes $7 million to repay the city for the Meals Avenue rebuild.

Made by our human newsroom with AI. Reviewed by Cale Green. How humans and AI work here · Grow with our newsroom ·

Source: City of Valdez, City of Valdez: 26-0449: City Manager Report 11.5 to 11.17.