The City of Valdez has added $38,965 to its construction management contract with DOWL, LLC for the Meals Avenue and Robe River Drive repaving project. The change raises the contract total from $591,938 to $630,903. The amendment was signed Oct. 12 and 13 and goes before the City Council as a report at its meeting at 7 pm Tuesday, Nov. 17, according to the meeting agenda.

The project covers Meals Avenue north of Pioneer Drive and Robe River Drive west to the Valdez High School parking lot. The council approved DOWL's original agreement on March 17, alongside a $6.3 million paving contract with Wolverine Supply, Inc. The agreement itself is dated March 24. The city's 2026 budget set aside $7 million for the work on the two streets.

DOWL manages field inspection and administration of the paving contractor's work, a role known as construction management. The firm's February proposal assumed the work would take no more than 21 weeks, at no more than six 11-hour days a week.

In an Oct. 12 letter to Valdez project manager Brad Sontag, DOWL senior project manager Eric Voorhees said the paving contractor began working seven days a week and more than 11 hours a day early in the project "due to being behind schedule."

DOWL field representative Roger Wirt arrived in Valdez the week of May 24, two weeks before the contractor began work. As of Oct. 10, Wirt had logged 20 weeks on site to the contractor's 18. DOWL asked to bill based on its own 20 weeks, since it had been paying for his labor, vehicle, lodging and per diem since he arrived.

Voorhees said DOWL had gone over the time-and-materials part of its budget, the part billed by hours and expenses actually incurred, by about $16,500. The amendment restores that amount. It also adds $1,365 for extra hours, $2,200 for per diem, lodging and vehicles, and $18,900 for one more week of on-site inspection at 13 hours a day, seven days a week. Voorhees said DOWL believes that week "will encompass the final week of paving."

The work is not done for the year. Voorhees said DOWL will prepare more amendments, including one for inspection in 2027, when Wolverine is expected to finish items that cannot be completed this fall.