The Mat-Su Borough Assembly will consider on Tuesday, Dec. 1, moving another $375,486 to finish American Charter Academy's new school near Wasilla. The money would come from Birchtree Charter School, a project the borough has put on hold.

The largest cost still ahead is a left-turn lane on Church Road that the Alaska Department of Transportation and Public Facilities requires the borough to design and build, according to a borough memo. The borough does not have a firm price. It expects the state's first formal design review in January 2027 to clarify the lane's scope and cost, and plans to build the lane that year.

A preliminary rough estimate in the memo for the state agreement the Assembly approved Sept. 1 put the lane at about $1.5 million. That night, project management division manager Cole Branham said that figure was for a standalone project. He said adding the lane to the state's Church Road pavement preservation project should bring costs down significantly.

"I don't want to stick to a hard number, but we're probably somewhere closer to like a quarter of a million dollars," Borough Manager Mike Brown said, adding that the total could depend on whether utilities must be moved. The memo does not say whether $375,486 will cover the lane and the school's other open costs.

The school is a two-story, 25,300-square-foot building on a 20-acre borough site near Church and Seldon roads. The borough said in 2025 it would address the limits of the converted strip mall the academy was using. The new memo says the building is substantially complete.

Earlier cost increases came mainly from water and utility problems, the memo says. Manganese in the well water forced the borough to install a drinking water cistern. Delays in permanent electrical service meant extended temporary power and extra trenching. The contractor says delays drilling a second well and approving the cistern hurt the schedule. Those costs are not yet fully counted.

The money for both schools comes from a school bond voters approved in November 2024. The borough set aside $15,155,000 for American Charter and $3,000,000 for Birchtree once the bonds were issued, a 2025 borough memo shows. In May, the Assembly moved $930,000 from Birchtree to the academy after a borough memo said water and power problems were expected to use up the project's contingency.

The proposed resolution would leave Birchtree with $1,694,514 and raise the academy's budget to $16,460,486. Branham told a joint Assembly and School Board meeting Sept. 8 that the borough is no longer proceeding with Birchtree because the school moved into Larson Elementary.

On May 19, Public Works Director Tom Adams floated flashing radar signs or a four-way stop instead of a lane. On Sept. 1, the Assembly voted 7-0 to authorize the agreement committing the borough to fund and build the lane, subject to Assembly appropriation. Branham said Sept. 8 that the state would issue a conditional driveway approval so the school could open.