The Matanuska-Susitna Borough Assembly will consider a $526,649 contract Tuesday to replace the single-lane Tuxedo Avenue bridge over Gene Creek in Willow with a crossing wide enough for two lanes of traffic.

Borough administration recommends awarding the work to Meier Excavation LLC, which submitted the lowest of four bids, according to the borough's action memorandum on the award.

The small bridge would come out, and an aluminum box culvert would go in its place.

Crews would also rebuild about 350 feet of road leading up to the crossing. The site is in Willow, near Mile 69.5 of the Parks Highway.

In Gene Creek itself, crews would divert the stream and pump water out of the work area during construction, then rebuild the streambed through the culvert to mimic a natural channel, a technique the borough's scope calls "stream simulation."

The borough already has Alaska Department of Fish and Game fish passage permits and U.S. Army Corps of Engineers permits for the work.

The other bids came from Caliber Construction Alaska at $641,750, Ahtna Construction Primary at about $822,000 and Granite Construction Company at about $854,000.

The borough had estimated the project would cost $500,000 to $700,000. The money would come from road service area capital project funds.

The contract would call for the work to be substantially done by Sept. 15, 2027, and finished by July 31, 2028.

A separate ordinance, introduced at the Assembly's Oct. 20 meeting, would extend the deadline to spend the project's funding from June 30, 2027, to Oct. 30, 2028.