Mat-Su asks for another $375,486 to finish American Charter Academy

by Cale Green · draft by Walter AlaskaNews
3 min readWasilla, Alaska

The Mat-Su Borough Assembly is set to decide Dec. 1 whether to move another $375,486 to finish American Charter Academy's new school northwest of Wasilla.

The money would come from Birchtree Charter School, a building project the borough has put on hold after that school moved into Larson Elementary. In May, the Assembly moved $930,000 from Birchtree to the academy. With both transfers, the academy's budget would rise from about $15.2 million to nearly $16.5 million, according to the proposed resolution.

The biggest cost still ahead is a left-turn lane on Church Road that the Alaska Department of Transportation and Public Facilities requires for the school's driveway permit. The borough doesn't have a firm price yet, according to a borough memo.

The school is a two-story, 25,300-square-foot building on 20 acres near Church and Seldon roads. It's meant to replace the converted strip mall the academy has been using and make room for more students. Borough Manager Mike Brown said in September that it would open around November. The new memo calls it substantially complete.

Most of the earlier cost increases came from water and power problems, the memo says. The first well drilled on the site had high levels of manganese, a naturally occurring metal. A second well came back the same, "actually a little bit higher," project management division manager Cole Branham told a joint Assembly and School Board meeting in September. The borough had to add an above-ground drinking water tank, and it is still weighing whether to treat the water, the memo says.

Delays getting permanent power to the site also meant running on temporary power longer and digging extra trenches. The contractor says delays drilling the second well and approving the tank affected its schedule. Those costs haven't been fully added up, the memo says.

The state required the turn lane after a traffic study. It found one is warranted by the traffic expected on Church Road by 2036 and the speeds drivers already travel there. In May, Public Works Director Tom Adams floated flashing radar signs or a four-way stop at Church and Seldon instead. "Those methods would be much less cost-intensive," he said.

A rough estimate in September put the lane at about $1.5 million. Brown called the early estimates "extremely high" and said the borough took the issue "all the way to the DOT commissioner."

Under an agreement the Assembly approved in September, the borough would design and pay for the lane, and the state has offered to build it as part of its 2027 repaving of Church Road. That would spare the borough overhead like traffic control, Brown said. He said he didn't want to "stick to a hard number," but put the borough's cost "somewhere closer to like a quarter of a million dollars," depending on whether utilities have to move.

"And frankly, a turn lane is probably a pretty good idea long term," he said.

The money for both schools comes from school bonds Mat-Su voters approved. Brown said in September that the project had already gone past what the bond proposition set for it. "We actually brought more money to the project to offset these unknowns, such as a turn lane and a water issue," he said.

The state's first formal design review in January should give a clearer idea of the lane's cost, the memo says. It doesn't say whether $375,486 will cover the lane and the school's other unfinished costs.

Made by our human newsroom with AI. Reviewed by Cale Green. How humans and AI work here · Grow with our newsroom ·

Source: Matanuska-Susitna Borough.