Ketchikan's Port and Harbors Department is routing storm overflow down Bar Harbor's northern boat ramp while crews prepare to replace a storm drain that failed Oct. 15, according to a Nov. 2 director's report in the Port and Harbors Advisory Board's November meeting materials.

Crews must dig up parts of the Bar Harbor parking lot to replace the drain. "This repair will be happening over the next month," Port and Harbors Director Wayne Phillips wrote in the report. A water diverter sends the overflow down the ramp until then.

The drain runs through the parking lot and under the site of the department's maintenance building. Its failure in the Oct. 15 storm caused significant flooding on Tongass Highway across from the Public Works and Harbor Master buildings, the report says. The maintenance building was evacuated and later demolished. The city already had a replacement shop out to bid and said it got "a good bid" at the same board meeting.

A City Council resolution confirming the local disaster emergency describes the failed line as a 48-inch stormwater pipe that collapsed under high water and washed out the soil around it.

City staff had found a partially crushed and offset section of the drain under the shop in August, along with corrosion and deformation, according to city records.

On Oct. 19 the city set up an emergency contract with P&T Construction, up to $99,000, to dig out and investigate the failed drain, divert the overflow and demolish the shop. On Nov. 5 the City Council authorized up to $150,999 more, bringing the contract to $249,999, according to the council meeting record. A Public Works memo says the money covers replacing the whole drain out to the ocean outfall, estimated at about $175,000, and repairs at two other damaged spots in the same drainage system, on Tongass Avenue and on Fifth Avenue.

The governor approved a state disaster declaration Oct. 17, and the city's preliminary damage estimate is over $4 million, according to the resolution.

At the board meeting, a member asked whether the city could be reimbursed for the demolished maintenance building. Both the building and the storm drain are potentially eligible, and Public Works and the city manager's office have applied, according to the board meeting record.