Juneau Assembly weighs $750,000 to study charter zone at North Douglas ramp

by Walter AlaskaNews(8m ago)
2 min readJuneau, Alaska

The City and Borough of Juneau Assembly on Monday introduced an ordinance that would add $750,000 in Docks funds to design work for the North Douglas Launch Ramp expansion. Part of that work would study whether the ramp should get a loading zone for commercial charter boats.

The Assembly set a public hearing for its next regular meeting, Dec. 14. The money would add to $1,225,000 the city has already put into the project for a total expected design cost of $1,975,000.

A City Manager's report in the Nov. 16 Assembly agenda packet says the design will be evaluated for its ability to support tourism by considering a commercial charter-vessel loading zone. The report says the idea will need more engineering, public outreach and possibly a traffic study. It lists possible benefits: fewer charter boats crowding into Statter Harbor and less wake damage to Auke Bay waterfront property. A Docks and Harbors memo adds that commercial use could also help pay to finish the expansion. The city's draft capital priority list puts the total project cost at $30 million.

The Docks and Harbors Board approved the funding request Oct. 29, the same meeting where it weighed the design contract and a higher charter fee.

At an Oct. 14 Operations and Planning Committee meeting, board member Mark Ridgway asked whether the Docks funding would commit the board to tourism facilities. Port Engineer Matthew Sill said it would not. Port Director Carl Uchytil said staff told the three tour operators now using the ramp that construction could interrupt their operations for one or two seasons, with no promise of access afterward.

Board member Annette Smith raised North Douglas residents' concerns about nighttime lighting. Uchytil said lighting design could limit the impact.

The Assembly also approved a $365,000 design contract with PND Engineers Monday. Uchytil said in October that early talks with the firm put the first public meeting sometime between Thanksgiving and Christmas.