Homer hires a manager for its 1964 harbor floats as the estimate tops $22 million

by Cale Green · draft by Walter AlaskaNewsFrom
2 min readHomer, Alaska

Homer has hired an Anchorage engineering firm to manage the replacement of its oldest harbor floats, a project now estimated at about $5 million more than the city has lined up.

The City Council approved a $681,217 contract with Moffatt & Nichol on Nov. 9, according to Resolution 26-069.

The floats, known as System 4, were built by the state in 1964 for the original Homer Harbor. The state handed them to the city in 1999 with extensive deferred maintenance, according to the city's capital improvement plan.

They are more than 30 years past their engineered life, the plan says. The headwalk float, the main walkway, is warped, with failing structure below the deck, rotting decking and hardware sticking up.

Shutting all of System 4 would affect 167 boats. The harbor already can't meet demand, and boats in Homer tie up as many as five deep. Closing even one finger of a float means boats have to raft up, move to transient moorage or, most likely, leave the harbor, the plan says.

Homer won an $11.2 million federal grant for the replacement this year, on its third try. But the estimate has climbed to slightly more than $22 million, from about $17 million when the city applied, Port Director Bryan Hawkins wrote in a Nov. 17 memo.

The U.S. Maritime Administration must approve any significant change for Homer to keep its grant, and staff doubt the city could trim more than $1 million without that review. Hawkins has urged the council to keep the full replacement and find the extra money.

Hawkins told the city's port commission Nov. 12 that the firm was hired to try to get costs under control, according to draft minutes. Moffatt & Nichol will also help with design reviews, permits and the grant paperwork, and oversee construction, which is planned for next fall.

Moffatt & Nichol scored highest on the city's criteria, though KPFF's proposal was cheaper, at $289,748. A Denali Commission grant pays for the contract.

The council hasn't approved construction yet. That will take a separate vote once the money is in place, and City Manager Melissa Jacobsen is to bring back a funding plan after the new year.