Downtown Wasilla would go one-way under an $83 million state project
Downtown Wasilla's street grid is about to go one-way. The state opens bids Sept. 25 on an $83 million project to reroute traffic through the historic town center, work that would run through 2028.
The design turns four streets into a "couplet," a pair of one-way corridors carrying traffic in opposite directions. Main Street and Knik-Goose Bay Road would run southbound; Talkeetna and Yenlo streets, extended, would run northbound, between Bogard Road and the Palmer-Wasilla Highway. It also builds a new intersection where the northbound corridor crosses both the Parks Highway and the Alaska Railroad, a spot the state says has a higher-than-average crash rate.
For the businesses and property owners along those four streets, the change is permanent. After two construction seasons, they lose two-way frontage for good. The project's comment record shows both support, from people who want the congestion eased, and worry about lost parking and the toll of construction on downtown businesses.
The project has grown more expensive and slower to arrive. As recently as last year the state planned to award it in fall 2025 and build in 2026 and 2027; construction is now pushed to 2027 and 2028. The combined construction-and-utilities figure rose about 26 percent between the 2024 plan and the current one, roughly $14 million more. The state's records don't explain why the timeline slipped or the cost climbed.
The design itself is old. It's the preferred alternative from a federal environmental finding signed in 2013, re-evaluated twice since, most recently in 2018. Acquiring the needed land, partial takings from 37 properties with no one displaced, was expected to wrap this summer. The records don't say what the state paid.
The bid records carry no position from the City of Wasilla, the borough or the railroad, and none of the three listed project contacts is quoted.
Source: Downtown Wasilla is about to be turned one way. The $83.6 million project was cleared in 2013, programmed for construction in 2025, and goes to bid on 25 September for work finishing in 2028 ().
AI-assisted, reviewed by Cale Green. Who is accountable.
Stay informed. Support what matters.
Free, permanent access to local news you can verify. Subscribe to support Walter AlaskaNews and go ad-free.
Related Coverage
Wasilla is hiring someone to write its next road plan, and a new parks plan too
Alaska News Β· 1w ago
A $293 million plan would rebuild and narrow Anchorage's downtown couplet
Alaska News Β· 1w ago
Wasilla weighs a plan to nearly double its airport runway
Alaska News Β· 3d ago
The 5th and 6th avenue rebuild just hit $370 million β and even planners are flagging "scope creep"
Alaska News Β· 1mo ago
Wasilla's sewer plan is 25 years old β and it's stalling development
Alaska News Β· 2mo ago

Comments
Sign in to leave a comment.
No comments yet. Be the first to share your thoughts.