by Cale Green · draft by Walter AlaskaNews(1mo ago)
1 min readPalmer, Alaska

Palmer wants to know whether the two wells that normally supply about 90% of its water can produce more. It cleared state environmental review Tuesday, Sept. 22, when the Alaska Department of Environmental Conservation issued a categorical exclusion for Wells 4 and 5, exempting it from further review.

Palmer has requested a $1.5 million state loan to analyze the wells and aquifer to gauge whether production can be increased, then design work that may include well and well-control upgrades and a standby emergency generator.

DEC found no significant effect on the facility's capacity, cultural resources, endangered species habitat or the human environment, and no significant public controversy. The notice sets no schedule and can be revoked if adverse information turns up.

The project is on the state drinking water priority list, the queue for Alaska Drinking Water Fund loans, whose plan lists $124.5 million available against $176.3 million requested. That list is a planning document, not a construction commitment.

DEC issued an earlier categorical exclusion for a Palmer new well and wellhouse in March 2025.