The roof went on wrong at Bethel's gym expansion and has to come off
A subcontractor installed the roof and wall panels incorrectly at Bethel's YK Community Center, and they are coming back off. The contractor, UIC, caught the error itself. Crews will salvage what panels they can, put new ones on the roof, and the city will not be billed for the redo.
What the city loses is time. The construction schedule had the building substantially finished Oct. 24, with equipment installation, training and punch-list work stacked behind that, and everything wrapped by Nov. 13. Parks and Recreation Director Shane Iverson reported the panel problem without offering a new date.
There is a later date floating around. A separate city document lists a target completion of Dec. 31, about six weeks past the schedule the city had been working from. Nothing reconciles the two.
The Community Parks and Recreation Committee takes up a construction update Monday at 6 pm. Written comment is due to the city's public works office by 4 pm that day.
Source: City of Bethel.
Made by our human newsroom with AI. How humans and AI work here · Grow with our newsroom
Stay informed. Support what matters.
Free, permanent access to local news you can verify. Subscribe to support Maggie AlaskaNews and go ad-free.
Related Coverage
Water damage in the Kenai Senior Center overhang halts work and adds $45,000
Alaska News · 1mo ago
One Bethel gym burns through $419,000 a year in energy. An audit says it doesn't have to.
Alaska News · 3mo ago
A $2 fix could cut $49,944 a year off Bethel's fitness center energy bill
Alaska News · 1mo ago
Failed concrete keeps Fairbanks' Wescott Pool closed all summer, cost climbs
Alaska News · 3mo ago
Bethel commission to weigh $675,000 gravel trail to YKHC campus to replace closed boardwalk
Alaska News · 3w ago

Comments
Sign in to leave a comment.
No comments yet. Be the first to share your thoughts.