The roof went on wrong at Bethel's gym expansion and has to come off
A subcontractor installed the roof and wall panels incorrectly at Bethel's YK Community Center, and they are coming back off. The contractor, UIC, caught the error itself. Crews will salvage what panels they can, put new ones on the roof, and the city will not be billed for the redo.
What the city loses is time. The construction schedule had the building substantially finished Oct. 24, with equipment installation, training and punch-list work stacked behind that, and everything wrapped by Nov. 13. Parks and Recreation Director Shane Iverson reported the panel problem without offering a new date.
There is a later date floating around. A separate city document lists a target completion of Dec. 31, about six weeks past the schedule the city had been working from. Nothing reconciles the two.
The Community Parks and Recreation Committee takes up a construction update Monday at 6 pm. Written comment is due to the city's public works office by 4 pm that day.
Source: City of Bethel ().
AI-assisted. No editor review is on record for this article. Who is accountable.
Stay informed. Support what matters.
Free, permanent access to local news you can verify. Subscribe to support Maggie AlaskaNews and go ad-free.
Related Coverage
One Bethel gym burns through $419,000 a year in energy. An audit says it doesn't have to.
Alaska News ยท 2mo ago
A $2 fix could cut $49,944 a year off Bethel's fitness center energy bill
Alaska News ยท 20h ago
Failed concrete keeps Fairbanks' Wescott Pool closed all summer, cost climbs
Alaska News ยท 2mo ago
Kodiak council to consider $1.2M ice rink roof contract, drawing from two parks funds
Alaska News ยท 2mo ago
Bethel would move sand shed money to road salt and water plant engineering
Alaska News ยท 2w ago
Comments
Sign in to leave a comment.
No comments yet. Be the first to share your thoughts.